Construction contract conditions
Contract conditions set out the principal legal relationship between the parties to a construction project, determining the allocation of risk and consequently, price.
English law, unlike the codified legal systems in Europe which recognise a duty of good faith, is not concerned with fairness but with certainty (unless it is a consumer contract protected by statute such as the Consumer Protection Act 1987 or the Unfair Contract Terms Act 1977).
The construction sector has a wide range of standard forms of contract which are intended to balance the risk of the parties but more importantly, through extensive and repeated use, give rise to a certainty of meaning. Well-known standard form contracts include the Joint Contracts Tribunal (JCT), the New Engineering Contract (NEC) and for international projects Fédération Internationale des Ingénieurs-Conseil (FIDIC).
See the article on Contracts for more information.
Standard form contracts also provide for different procurement routes, such as:
- Construction management.
- Design and build.
- Design build finance and operate (PPP / PFI / DBO / BOOT).
- Emerging cost contracts.
- Engineering Procurement and Construction Contract (EPC) / Turnkey contract
- Engineering Procurement and Construction Management contract (EPCM)
- Furniture, Fixtures and Equipment contract (FF&E).
- Framework agreements.
- Management contract.
- Measured term contracts
- Measurement contract ('re-measurement' or ‘measure and value’ contract)
- Partnering.
- Prime cost contract / cost plus contract / cost reimbursable contract
- Prime contracting / prime-type contracting
- Traditional contract.
See the article on Procurement routes for more information.
Typical conditions found in construction contracts can include (in alphabetical order):
- Access to the construction site.
- Assignment, rights of third parties and collateral warranties.
- Commissioning.
- Contractor's design.
- Contract sum and adjustment,
- Date for possession, deferment of possession, progress, delays, completion date, suspension of works and termination.
- Dispute resolution procedures and alternative dispute resolution.
- Employer's instructions.
- Force majeure.
- Information release schedule.
- Insolvency.
- Injury, damage and insurance.
- Joint Fire Code.
- Liquidated damages.
- Net contribution clause.
- Partial possession.
- Payment, valuation (including off-site materials), certificates, fluctuations and retention.
- Practical completion.
- Project management and contract administration.
- Quality of works.
- Relevant events (compensation events), extensions of time and loss and expense.
- Sectional completion.
- Statutory obligations.
- Sub-contractors.
- Testing and defects (defects liability period)
- Variations, prime cost sums and provisional sums.
Conditions of contract must be read in conjunction with specification documents, drawings bills of quantities, activity schedules and special conditions. Standard form contracts often comprise suites of contracts with ‘back to back’ subcontracts, consultant appointments and collateral warranties. The use of core conditions with option schedules or supplemental provisions is also now common (see NEC contract).
[edit] Related articles on Designing Buildings
- Addendum.
- Alternative dispute resolution.
- Articles of agreement.
- Common law.
- Competitive procedure with negotiation.
- Condition.
- Construction contract.
- Construction law.
- Contract administrator.
- Contract negotiations.
- Contract strategy.
- Contractual right.
- Delay damages.
- Disallowed cost.
- Escalation.
- Essentials of a contract.
- Excepted risk.
- Extension of time.
- Form of tender.
- Hybrid construction contract.
- Key dates.
- Liquidated damages.
- Loss and expense.
- Modifying clauses in standard forms of contract.
- Named specialist work.
- Negotiated Procedure without Prior Publication NPwPP.
- Outturn cost.
- Payment for extra work.
- Pre-contract management.
- Proprietary information.
- Quantum meruit.
- Right to payment.
- Supply chain management.
- Variation.
- Z clauses.
Featured articles and news
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description fron the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.


























Comments
this site is indeed very informative👍 worth to spend sometime reading during work break