Escalation
Civil Engineering Procedure, 7th edition, published by the Institution of Civil Engineers (ICE) defines ‘escalation’ as an: 'Increases (or decreases) in the costs of labour or materials due to inflation (or recession and deflation).'
Some contracts make provisions for contract price adjustment to allow for the effects of escalation based on data about changes in the cost of commodities, labour, fuel and so on. Such allowances might be referred to as ‘fluctuations’ as there is a fluctuating price in the contract (although fluctuations generally also allow for changes in taxation and increases in head office or administrative costs).
On smaller projects of a short duration, the contractor may be expected to have taken the effects of escalation into account when calculating their price, and they may be able to hold sub-contractors and suppliers to agreed prices for the duration of the contract.
On larger projects, typically lasting more than a year, the contractor may be asked to tender based on prices at an agreed base date, and then the contract makes provisions for escalation to specified items over the duration of the project, such as fuel, steel and so on.
Determining the actual amount of escalation for each item would be very time consuming, and so calculations are generally based on agreed indices, such as public records, JCT bulletins and so on.
Escalation can be caused by issues such as:
- An overheating construction industry.
- Natural disasters.
- Exchange rate changes.
- Changes to regulations.
- Supply problems.
- Labour shortages.
- Inflation in the wider economy, such as fuel price increases or wage increases.
- Global economic conditions.
Escalation clauses put the client at risk, as the final price is not known when the contract is agreed. It is sensible therefore for clients to forecast likely escalation during the course of the project and to make allowances for this, with a contingency provision.
Significant escalation which has not been allowed for can result in the scope of projects being reduced, and can even bring projects to a halt.
However, if there were no escalation provisions, the contractor would have to bear all the risk of price changes, and this would be reflected in their tender.
NB ICMS: Global Consistency in Presenting Construction Life Cycle Costs and Carbon Emissions, 3rd edition, November 2021, published by the ICMS (International Cost Management Standard) Coalition, defines escalation as: ‘A positive or negative factor or rate reflecting an estimate of differential increase/decrease in the general price level for a particular commodity, or group of commodities, or resources (ISO 15686-5).’
See also: Escalation clause and Fluctuations.
[edit] Related articles on Designing Buildings
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.






















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.