Datum
On a construction project, a datum level is an arbitrary horizontal plane of reference from which all vertical dimensions are measured. It can show the vertical height difference between floor levels of a building as well as differences in levels between one part of the site and another.
The datum on a site can be given a 0.000m designation but this does not have to necessarily be outside ground level; if it is, a ground floor may be at say, 0.750m and a first floor at 4.750 and so on proceeding up the building. In contrast, a basement which will be below ground will be below datum level and will therefore have a minus symbol prefixed to it e.g -3.250m.
However, minus signs can be easily misread, not seen or read as a dash, so can cause confusion. For this reason, a suitable fixed point (called a temporary benchmark – TBM) is assumed to ensure that all other levels are positive. So, in the case of the basement level referred to above, it may be given 0.000m as the site datum, in which case (following the logic from above) ground level = 3.250m; ground floor = 4.000m; first floor = 8.000m and so on. The levels usually refer to finished floor levels (FFL) but can also indicate other features e.g finished structural level (FSL)
Datum levels are useful as they provide points of reference to allow the vertical setting out of buildings and how they relate to other levels on a site. They should be clearly indicated on all relevant drawings with all levels described in metres to three decimal places but always as positive numbers because they are above datum level.
It is increasingly the case, especially for large projects, that the Ordnance Survey (OS) datum is used as a project datum as it allows work on the site to be related to other features in the area, e.g manholes and sewers, local gradients etc. Using this approach means that everything is to the same OS datum and OS grid (OSG).
Note: OS datum is taken as height above sea-level based on a known datum point at Newlyn, Cornwall; if the OS datum is being used, it must be indicated on the drawings. OSG is the standard known grid across the UK.
For more information see: Ordnance datum.
[edit] Other datums
A datum may also be a line from which all other horizontal dimensions relate to whether, on architectural or engineering drawings. An example is a building that has a plan generated from a back wall.
A datum may also be a point that is used for setting out the building. This must be clearly marked on drawings to help the contractor’s setting out. For example, a circular building will be set out from a datum point from which all radii are generated.
Drawing for Understanding, Creating Interpretive Drawings of Historic Buildings, published by Historic England in 2016 defines a datum line as: 'A horizontal or vertical reference line used to control height and horizontal distance measurements.'
The Geospatial Glossary, published by the Geospatial Commission, and accessed on 17 September 2022, defines horizontal datums as: ‘…a series of data points on the surface of the earth that are used to measure the position of oneself on the Earth’s surface.’
[edit] Related articles on Designing Buildings
- At grade.
- Data.
- Ordnance Survey.
- Origin point.
- Geographic information system GIS.
- Global positioning systems and global navigation satellite systems.
- Building height.
- International Property Measurement Standards.
- Invert.
- Location plan.
- Measurement.
- Ordnance datum.
- Setting out.
- Site plan.
- Water engineering.
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments