Datum
On a construction project, a datum level is an arbitrary horizontal plane of reference from which all vertical dimensions are measured. It can show the vertical height difference between floor levels of a building as well as differences in levels between one part of the site and another.
The datum on a site can be given a 0.000m designation but this does not have to necessarily be outside ground level; if it is, a ground floor may be at say, 0.750m and a first floor at 4.750 and so on proceeding up the building. In contrast, a basement which will be below ground will be below datum level and will therefore have a minus symbol prefixed to it e.g -3.250m.
However, minus signs can be easily misread, not seen or read as a dash, so can cause confusion. For this reason, a suitable fixed point (called a temporary benchmark – TBM) is assumed to ensure that all other levels are positive. So, in the case of the basement level referred to above, it may be given 0.000m as the site datum, in which case (following the logic from above) ground level = 3.250m; ground floor = 4.000m; first floor = 8.000m and so on. The levels usually refer to finished floor levels (FFL) but can also indicate other features e.g finished structural level (FSL)
Datum levels are useful as they provide points of reference to allow the vertical setting out of buildings and how they relate to other levels on a site. They should be clearly indicated on all relevant drawings with all levels described in metres to three decimal places but always as positive numbers because they are above datum level.
It is increasingly the case, especially for large projects, that the Ordnance Survey (OS) datum is used as a project datum as it allows work on the site to be related to other features in the area, e.g manholes and sewers, local gradients etc. Using this approach means that everything is to the same OS datum and OS grid (OSG).
Note: OS datum is taken as height above sea-level based on a known datum point at Newlyn, Cornwall; if the OS datum is being used, it must be indicated on the drawings. OSG is the standard known grid across the UK.
For more information see: Ordnance datum.
[edit] Other datums
A datum may also be a line from which all other horizontal dimensions relate to whether, on architectural or engineering drawings. An example is a building that has a plan generated from a back wall.
A datum may also be a point that is used for setting out the building. This must be clearly marked on drawings to help the contractor’s setting out. For example, a circular building will be set out from a datum point from which all radii are generated.
Drawing for Understanding, Creating Interpretive Drawings of Historic Buildings, published by Historic England in 2016 defines a datum line as: 'A horizontal or vertical reference line used to control height and horizontal distance measurements.'
The Geospatial Glossary, published by the Geospatial Commission, and accessed on 17 September 2022, defines horizontal datums as: ‘…a series of data points on the surface of the earth that are used to measure the position of oneself on the Earth’s surface.’
[edit] Related articles on Designing Buildings
- At grade.
- Data.
- Ordnance Survey.
- Origin point.
- Geographic information system GIS.
- Global positioning systems and global navigation satellite systems.
- Building height.
- International Property Measurement Standards.
- Invert.
- Location plan.
- Measurement.
- Ordnance datum.
- Setting out.
- Site plan.
- Water engineering.
Featured articles and news
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
Comments