Finished floor level
Contents |
[edit] What is the finished floor level?
Finished floor level (FFL) refers to the uppermost surface of a floor once construction has been completed but before any finishes have been applied. So, in concrete construction it may be the uppermost surface of a screeded finish, or in timber construction, FFL will denote the top level of floorboards, chipboard or ply decking.
Finished floor level does not take into account any applied finishes as these may be added by owners, occupiers or tenants, will vary in thickness, e.g a thick shag-pile carpet has different thickness to a laminated floor, and may be replaced.
[edit] How is finished floor level expressed?
Floor levels and other vertical dimensions are usually expressed in metres to three decimal places, e.g FFL 16,550. On construction drawings (plans, sections and elevations), finished floor level may be abbreviated ‘FFL 27,000’, the figure suffixed denoting the level in metres above a defined datum level (usually outside ground level or ground floor level). The floor above may be FFL 31,000 and the floor below FFL 23,000.
On some large projects, the job datum may be related to the Ordnance datum - the height of mean sea-level, taken from a reference point at Newlyn in Cornwall. Where there is the possibility of a minus datum figure, the minus sign may be misread or cause confusion if included in FFL data. In these circumstances, a temporary bench mark (TBM) may be introduced to ensure all other levels are positive.
To differentiate between existing and intended (to be constructed) levels, the latter will usually have a rectangle around the numbers. In addition, the numbers may be beside or above an arrow that indicates the finished floor level. On a plan, the exact position where the figure applies is usually indicated by an ‘x’.
[edit] What are the benefits of measuring finished floor levels?
As each floor will have a different level, the FFL figures will have been produced by a measured survey and serve to confirm that:
- The floor levels are correct and have been constructed according to plan.
- Subtracting one floor level from say, the one above can give the FFL-to-FFL storey height.
- They give an indication of the levels relative to ground level, adjacent buildings or other buildings on the site. This is particularly useful when physical links, ramps or walkways must be constructed between buildings.
- FFL figures can be transposed onto elevations to indicate relative floor levels and their relation to the facade.
[edit] Related articles on Designing Buildings
Featured articles and news
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
"So you could potentially end up with a variety of screed levels across the same floor due to varying finish build up? i.e. marble/ carpet/ timber etc. Where's common sense when you need it."
In response to above ^
It is very rare that finishes are known when you begin to design a building (hence this being the sensible working definition for FFL).
Adjustments for things like an unusually thick wearing finish would typically see the screed in the localised area adjusted. This adjustment would then be denoted on applicable plans/section as a +/- from the building FFL for that level.
The minimal difference between carpet/tile etc. is lost in threshold strips.
Hope that makes sense.