Invert
[edit] Introduction
In a pipe, sewer, channel or tunnel, the invert is the lowest point upon which water can flow on the inside. If circular in shape, the invert is the lowest point on the inner circle if looking at a section of the construction. The invert may be considered the 'floor level' of the vessel in question.
In a tunnel constructed by drill and blast or by NATM (New Austrian Tunnelling Method), the invert will vary according to the stage of the construction: the invert will always be the lowest point inside that has been excavated at that point in time. This will become lower as the excavation proceeds, with the final invert level being that of the complete tunnel.
Also, a tunnel being constructed using NATM (sometimes called 'sequential excavation') may have two or three varying inverts as excavation of the centre and sides of the tunnel may be at different stages.
An invert will typically be laid to a gradient, particularly if it is to convey liquids, such as in a pipe or sewer. The level of the gradient will therefore vary according to the position of the invert along the flow.
The invert level is usually given as a distance to some fixed point. In tunnel construction, invert level may be cited as 10m above tunnel datum (ATD) where the tunnel datum (based on an ordnance datum) is set at a particular level for the entire project. Alternatively, a survey of a property for a preliminary design may record the varying invert levels of the drainage system beneath the building.
In contrast, the ‘crown’ of the tunnel or pipe is that point located on the top external surface that is directly above the invert. One way to calculate the crown position is by adding (or subtracting) the internal diameter and the material’s thickness to (or from) the invert level.
For example, if a 10m-internal diameter tunnel of circular-section with uniform 500mm thickness and an invert level of 16m below ground level, the crown level would be established by subtracting from the invert level the internal diameter (10m) plus subtracting the material thickness, which is equivalent to: 16m – 10m – 0.5m = 5.5m.
So, the crown datum level is at 5.5m below ground.
Sometimes it may be necessary to reverse this calculation when the crown is known and the invert level is not known.
Manhole Design & invert level.
The of the manhole is kept equal to the invert level of the sewer line. A manhole is dug 2 feet below the invert level, and a layer of concrete is poured up to the invert level, then filled with concrete half the pipe height with a little dry concrete to match the size of the round pipe. Is. , which makes the manhole look like a conduit in reverse.
If the pipes are coming from different sides in the main hole, the pipe is diverted towards the main pipe at a suitable slope with the help of concrete as per the occasion. And it is also called manhole bunching in engineering.
And it is smoothed from the top so that the material flowing from the reverse surface of the manhole easily enters the pipeline of the manhole. The measurement from the invert level of the manhole to the top surface of the manhole is called the height of the manhole.
[edit] Related articles on Designing Buildings
- At grade.
- Adit.
- Caisson.
- Cofferdam.
- Controlled waters.
- Datum.
- Drainage.
- Ordnance Datum.
- Construction acronyms.
- Trenchless technology.
- Tunnelling.
[edit] External Links
https://routineconstruction.com/what-is-invert-level-in-sewer-calculation-of-invert-level/surveying/ invert level
Featured articles and news
The sad story of Derby Hippodrome
An historic building left to decay.
ECA, JIB and JTL back Fabian Society call to invest in skills for a stronger built environment workforce.
Women's Contributions to the Built Environment.
Calls for the delayed Circular Economy Strategy
Over 50 leading businesses, trade associations and professional bodies, including CIAT, and UKGBC sign open letter.
The future workforce: culture change and skill
Under the spotlight at UK Construction Week London.
A landmark moment for postmodern heritage.
A safe energy transition – ECA launches a new Charter
Practical policy actions to speed up low carbon adoption while maintaining installation safety and competency.
Frank Duffy: Researcher and Practitioner
Reflections on achievements and relevance to the wider research and practice communities.
The 2026 Compliance Landscape: Fire doors
Why 'Business as Usual' is a Liability.
Cutting construction carbon footprint by caring for soil
Is construction neglecting one of the planet’s most powerful carbon stores and one of our greatest natural climate allies.
ARCHITECTURE: How's it progressing?
Archiblogger posing questions of a historical and contextual nature.
The roofscape of Hampstead Garden Suburb
Residents, architects and roofers need to understand detailing.
Homes, landlords. tenants and the new housing standards
What will it all mean?


















