Invert
[edit] Introduction
In a pipe, sewer, channel or tunnel, the invert is the lowest point upon which water can flow on the inside. If circular in shape, the invert is the lowest point on the inner circle if looking at a section of the construction. The invert may be considered the 'floor level' of the vessel in question.
In a tunnel constructed by drill and blast or by NATM (New Austrian Tunnelling Method), the invert will vary according to the stage of the construction: the invert will always be the lowest point inside that has been excavated at that point in time. This will become lower as the excavation proceeds, with the final invert level being that of the complete tunnel.
Also, a tunnel being constructed using NATM (sometimes called 'sequential excavation') may have two or three varying inverts as excavation of the centre and sides of the tunnel may be at different stages.
An invert will typically be laid to a gradient, particularly if it is to convey liquids, such as in a pipe or sewer. The level of the gradient will therefore vary according to the position of the invert along the flow.
The invert level is usually given as a distance to some fixed point. In tunnel construction, invert level may be cited as 10m above tunnel datum (ATD) where the tunnel datum (based on an ordnance datum) is set at a particular level for the entire project. Alternatively, a survey of a property for a preliminary design may record the varying invert levels of the drainage system beneath the building.
In contrast, the ‘crown’ of the tunnel or pipe is that point located on the top external surface that is directly above the invert. One way to calculate the crown position is by adding (or subtracting) the internal diameter and the material’s thickness to (or from) the invert level.
For example, if a 10m-internal diameter tunnel of circular-section with uniform 500mm thickness and an invert level of 16m below ground level, the crown level would be established by subtracting from the invert level the internal diameter (10m) plus subtracting the material thickness, which is equivalent to: 16m – 10m – 0.5m = 5.5m.
So, the crown datum level is at 5.5m below ground.
Sometimes it may be necessary to reverse this calculation when the crown is known and the invert level is not known.
Manhole Design & invert level.
The of the manhole is kept equal to the invert level of the sewer line. A manhole is dug 2 feet below the invert level, and a layer of concrete is poured up to the invert level, then filled with concrete half the pipe height with a little dry concrete to match the size of the round pipe. Is. , which makes the manhole look like a conduit in reverse.
If the pipes are coming from different sides in the main hole, the pipe is diverted towards the main pipe at a suitable slope with the help of concrete as per the occasion. And it is also called manhole bunching in engineering.
And it is smoothed from the top so that the material flowing from the reverse surface of the manhole easily enters the pipeline of the manhole. The measurement from the invert level of the manhole to the top surface of the manhole is called the height of the manhole.
[edit] Related articles on Designing Buildings
- At grade.
- Adit.
- Caisson.
- Cofferdam.
- Controlled waters.
- Datum.
- Drainage.
- Ordnance Datum.
- Construction acronyms.
- Trenchless technology.
- Tunnelling.
[edit] External Links
https://routineconstruction.com/what-is-invert-level-in-sewer-calculation-of-invert-level/surveying/ invert level
Featured articles and news
Key points for construction at a glance with industry reactions.
Functionality, visibility and sustainability
The simpler approach to specification.
Architects, architecture, buildings, and inspiration in film
The close ties between makers and the movies, with our long list of suggested viewing.
SELECT three-point plan for action issued to MSPs
Call for Scottish regulation, green skills and recognition of electrotechnical industry as part of a manifesto for Scottish Parliamentary elections.
UCEM becomes the University of the Built Environment
Major milestone in its 106-year history, follows recent merger with London School of Architecture (LSE).
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.