Invert
[edit] Introduction
In a pipe, sewer, channel or tunnel, the invert is the lowest point upon which water can flow on the inside. If circular in shape, the invert is the lowest point on the inner circle if looking at a section of the construction. The invert may be considered the 'floor level' of the vessel in question.
In a tunnel constructed by drill and blast or by NATM (New Austrian Tunnelling Method), the invert will vary according to the stage of the construction: the invert will always be the lowest point inside that has been excavated at that point in time. This will become lower as the excavation proceeds, with the final invert level being that of the complete tunnel.
Also, a tunnel being constructed using NATM (sometimes called 'sequential excavation') may have two or three varying inverts as excavation of the centre and sides of the tunnel may be at different stages.
An invert will typically be laid to a gradient, particularly if it is to convey liquids, such as in a pipe or sewer. The level of the gradient will therefore vary according to the position of the invert along the flow.
The invert level is usually given as a distance to some fixed point. In tunnel construction, invert level may be cited as 10m above tunnel datum (ATD) where the tunnel datum (based on an ordnance datum) is set at a particular level for the entire project. Alternatively, a survey of a property for a preliminary design may record the varying invert levels of the drainage system beneath the building.
In contrast, the ‘crown’ of the tunnel or pipe is that point located on the top external surface that is directly above the invert. One way to calculate the crown position is by adding (or subtracting) the internal diameter and the material’s thickness to (or from) the invert level.
For example, if a 10m-internal diameter tunnel of circular-section with uniform 500mm thickness and an invert level of 16m below ground level, the crown level would be established by subtracting from the invert level the internal diameter (10m) plus subtracting the material thickness, which is equivalent to: 16m – 10m – 0.5m = 5.5m.
So, the crown datum level is at 5.5m below ground.
Sometimes it may be necessary to reverse this calculation when the crown is known and the invert level is not known.
Manhole Design & invert level.
The of the manhole is kept equal to the invert level of the sewer line. A manhole is dug 2 feet below the invert level, and a layer of concrete is poured up to the invert level, then filled with concrete half the pipe height with a little dry concrete to match the size of the round pipe. Is. , which makes the manhole look like a conduit in reverse.
If the pipes are coming from different sides in the main hole, the pipe is diverted towards the main pipe at a suitable slope with the help of concrete as per the occasion. And it is also called manhole bunching in engineering.
And it is smoothed from the top so that the material flowing from the reverse surface of the manhole easily enters the pipeline of the manhole. The measurement from the invert level of the manhole to the top surface of the manhole is called the height of the manhole.
[edit] Related articles on Designing Buildings
- At grade.
- Adit.
- Caisson.
- Cofferdam.
- Controlled waters.
- Datum.
- Drainage.
- Ordnance Datum.
- Construction acronyms.
- Trenchless technology.
- Tunnelling.
[edit] External Links
https://routineconstruction.com/what-is-invert-level-in-sewer-calculation-of-invert-level/surveying/ invert level
Featured articles and news
We're expanding our collaborative mission by launching DB Intelligence, an exclusive market research advisory panel. Built environment professionals can now get paid to share their expertise on industry trends, products and services.
Panel members receive direct financial incentives for participating in research projects like short surveys, 1-2-1 interviews and focus groups. Register today to shape the future of the construction sector.
Planning condition discharge in England and Wales
A brief exoplanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
The latest of eight Skills England apprenticeship units
The addition of battery manufacturing welcomed by ECA with a warning about the risks of fast-tracked apprenticeship units.
Building Control Independent Panel final report
A precis of a key report led by Dame Hackitt with full recommendations and link to the government response.
Building Safety recap April, 2026
A short and longer run-through of the month, with links to further information and sources.
CIAT May 2026 briefing.
From medieval scribes to modern word art.
ECA welcomes crackdown on late payment and push for clean energy, whilst CIOB seek fixed cladding removal timeframes.
Cyber Security in the Built Environment
Protecting projects, data, and digital assets: A CIOB Academy TIS.
Managing competence in the built environment
ITFG publishes new industry guide on how to meet the ICC principles.
The UK's campaign to reduce noise pollution: Mythbusting, articles and topic guides.




















