Invert
[edit] Introduction
In a pipe, sewer, channel or tunnel, the invert is the lowest point upon which water can flow on the inside. If circular in shape, the invert is the lowest point on the inner circle if looking at a section of the construction. The invert may be considered the 'floor level' of the vessel in question.
In a tunnel constructed by drill and blast or by NATM (New Austrian Tunnelling Method), the invert will vary according to the stage of the construction: the invert will always be the lowest point inside that has been excavated at that point in time. This will become lower as the excavation proceeds, with the final invert level being that of the complete tunnel.
Also, a tunnel being constructed using NATM (sometimes called 'sequential excavation') may have two or three varying inverts as excavation of the centre and sides of the tunnel may be at different stages.
An invert will typically be laid to a gradient, particularly if it is to convey liquids, such as in a pipe or sewer. The level of the gradient will therefore vary according to the position of the invert along the flow.
The invert level is usually given as a distance to some fixed point. In tunnel construction, invert level may be cited as 10m above tunnel datum (ATD) where the tunnel datum (based on an ordnance datum) is set at a particular level for the entire project. Alternatively, a survey of a property for a preliminary design may record the varying invert levels of the drainage system beneath the building.
In contrast, the ‘crown’ of the tunnel or pipe is that point located on the top external surface that is directly above the invert. One way to calculate the crown position is by adding (or subtracting) the internal diameter and the material’s thickness to (or from) the invert level.
For example, if a 10m-internal diameter tunnel of circular-section with uniform 500mm thickness and an invert level of 16m below ground level, the crown level would be established by subtracting from the invert level the internal diameter (10m) plus subtracting the material thickness, which is equivalent to: 16m – 10m – 0.5m = 5.5m.
So, the crown datum level is at 5.5m below ground.
Sometimes it may be necessary to reverse this calculation when the crown is known and the invert level is not known.
Manhole Design & invert level.
The of the manhole is kept equal to the invert level of the sewer line. A manhole is dug 2 feet below the invert level, and a layer of concrete is poured up to the invert level, then filled with concrete half the pipe height with a little dry concrete to match the size of the round pipe. Is. , which makes the manhole look like a conduit in reverse.
If the pipes are coming from different sides in the main hole, the pipe is diverted towards the main pipe at a suitable slope with the help of concrete as per the occasion. And it is also called manhole bunching in engineering.
And it is smoothed from the top so that the material flowing from the reverse surface of the manhole easily enters the pipeline of the manhole. The measurement from the invert level of the manhole to the top surface of the manhole is called the height of the manhole.
[edit] Related articles on Designing Buildings
- At grade.
- Adit.
- Caisson.
- Cofferdam.
- Controlled waters.
- Datum.
- Drainage.
- Ordnance Datum.
- Construction acronyms.
- Trenchless technology.
- Tunnelling.
[edit] External Links
https://routineconstruction.com/what-is-invert-level-in-sewer-calculation-of-invert-level/surveying/ invert level
Featured articles and news
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.

























