Cofferdam
Contents |
[edit] Introduction
Cofferdams are temporary structures used where construction is being carried out in areas submerged in water. They are most commonly used to facilitate the construction or repair of dams, piers and bridges. The aim of a cofferdam is to be as watertight as possible to create a dry area in which to complete the required building works, or at least to limit water ingress to a safe level that can be pumped away.
Cofferdams must be able to withstand very high pressures and can create a hazardous situation if they are installed incorrectly. They are usually constructed using steel sheet piles driven into the ground and supported by internal braces and cross braces. Timber sheet piles, concrete or a combination of materials can also be used.
A cofferdam can be any shape. Its design will be depend on the depth required, the required working area, soil conditions, fluctuations in the water level, and so on.
[edit] Types of cofferdam
There are several different types of cofferdam. The most common are as follows:
[edit] Typical piled cofferdam
The construction sequence for a typical piled cofferdam is as follows:
- Pre-dredge the proposed area of the cofferdam.
- Drive temporary support piles into place.
- Install bracing frames to support piles.
- Drive sheet piles into place.
- Pump out water from the inside of the cofferdam.
- Progressively install internal bracing as required.
- Excavate ditch to allow leakage to run to one place.
- Place rock fill as a leveling and support course.
[edit] Earthen
This is a simple form of cofferdam suitable for areas of shallow water with low current velocity, where a sloped earthen embankment is built up around the area to be enclosed. The bank should be a combination of clay and sand or clay and gravel.
[edit] Rock-fill
If the water to be retained is not shallow enough for an earthen cofferdam, stone or rubble can be used instead. The stones are built up in the required shape of the cofferdam, and voids filled with earth, gravel or stone-chips.
[edit] Single-walled
This type of cofferdam is most suitable when the area to be enclosed is particularly small and the water is of a deeper level, roughly 4-6 m. Guide piles made of timber are driven into the ground and bracing constructed before sheet piles are driven into place and secured to the bracing using bolts.
[edit] Double-walled
Single-walled cofferdams become unfeasible as larger areas are required in deeper water, and so double-walled cofferdams are sometimes necessary. Two walls are built with a gap between them, the thickness of which is dependent upon the depth of water.
The general rule is for the thickness of the wall to equal the depth of water up to 3 m, greater depths require 3 m plus half the excess depth. The two wall faces are connected at the top using steel rods placed at close intervals.
[edit] Crib
This is commonly used in deep waters where the ground is particularly hard. The sheet piles are supported by a horizontal framework of timbers, known as cribs, which form pockets to be filled with earth or stones. This is constructed on land prior to being moved into position in the water. The crib is sunk into position, the internal space filled with stone or other material and timber or steel piles are then driven around the boundary of the crib.
[edit] Cellular
This type of cofferdam is most suitable for deep water areas, most commonly for during marine construction such as dams and wharves. Straight web steel sheet piles are driven into the ground to form a series of inter-connected cells of specific shapes which are filled with clay, sand or gravel to enable the structure to withstand the lateral forces of the water pressure. There are two common shapes:
- Circular type: Each cell acts as a self-supporting independent unit so each cell can be completely filled before construction of the next cell begins.
- Diaphragm type: Made from interconnected steel sheet piles using circular arcs at the inner and outer sides. The cells are then filled with coarse-grained soils, all at the same rate to avoid rupturing.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Bridge construction.
- Caisson.
- Coastal defences.
- Difference between cofferdams and caissons.
- Driven piles.
- Formwork.
- Geothermal pile foundations.
- Groundwater control in urban areas.
- Grouting in civil engineering.
- Micropiles.
- Pile foundations.
- Pumps and dewatering equipment.
- Retaining walls.
- River engineering.
- Screw piles.
- Sheet piles.
- Shoring.
- Temporary works.
- Trench box.
- Underpinning.
- Underwater foundations.
- Watercourse.
- Water engineering.
[edit] External references
- Deep excavation - Cofferdams
- The Construction Civil - Types of cofferdam
Featured articles and news
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.