Sheet piles
Contents |
[edit] Introduction
Sheet piles are sections of sheet materials with interlocking edges that are driven into the ground to provide earth retention and excavation support. Sheet piles are most commonly made of steel, but can also be formed of timber or reinforced concrete.
Sheet piles are commonly used for retaining walls, land reclamation, underground structures such as car parks and basements, in marine locations for riverbank protection, seawalls, cofferdams, and so on.
The selection of sheet piling is dependent on factors, such as:
- The type of work, for example. whether it is permanent or temporary.
- Site conditions.
- The required depth of piles.
- The bending moments involved.
- The nature of the structure.
- The type of protection required.
[edit] Timber sheet piles
Timber sheet piles are generally used for short spans in temporary structures, and to resist light lateral loads. They are typically connected together by tongue and groove joints. The disadvantage of timber piles is that they require preservative treatment and are not generally suitable for soils consisting of stones.
[edit] Reinforced concrete sheet piles
Reinforced concrete sheet piles are formed using precast concrete members, usually connected together by tongue and groove joints. They are commonly used in permanent river embankments, canals and other marine structures. The toes of the piles are usually cut with an oblique face to facilitate easy driving and interlocking, while the heads are finished off by casting a capping beam.
[edit] Steel sheet piles
Steel is the most common form of sheet piles as it has good resistance to high driving stresses, excellent water-tightness, and can be increased in length either by welding or bolting. They are connected by interlocking.
There are four basic forms of steel sheet piles:
[edit] Normal sections
These include Larssen and Frodingham sheet piles, which are systems of interlocking steel piles. They have good driving qualities and are designed to provide good strength for low weight.
The interlocking system facilitates easy positioning of the piles (pitching) and driving, as well as providing a close-fitting joint to form an effective water seal. In some cases, a sealant can be brushed into the joints prior to pitching which expands in thickness to form a watertight joint.
Larssen sheet piles are stronger and easier to drive because of their uniform section shape. Frodingham sheet piles are usually supplied interlocked in pairs, which makes them easier and quicker to handle and pitch.
[edit] Straight web sections
These are piles that are interlocked and driven to form cellular cofferdams which may be filled with material such as gravel and small rocks.
[edit] Box sections
These are formed by two or more sheet pile sections welded together and are suitable when heavy loads and high bending moments are anticipated.
[edit] Composite sections
These are commonly used in waterfront protection where large bending moments and heavy axial loads are anticipated. A typical composite pile is a double Frodingham section welded to the flange of a universal I-beam.
[edit] Installation
Prior to installation, piles should be carefully inspected for straightness, cracks, and the integrity of the interlocking components.
Driving must be carefully monitored and should stop immediately if the pile ceases to penetrate the soil, before moving on to the next pile along. In some cases, several adjacent piles will be unable to penetrate to the design depth. At this point, effort should be made to remove the obstacle, either by partial excavation or using a water jet. There is an acceptable number of ‘under-driven’ sheet piles, but this will vary according to the specific design requirements.
Sheet piles have a tendency to deviate from a vertical plane during driving and instead lean sideways. This is due to encountering obstacles within the soil which act as deflection. Guide controls should be used to counter this.
One technique is to drive piles in panels. This involves pitching and driving two piles to part or full-penetration at either end of a panel of piles. The panel is therefore supported by the ‘bookended’ piles during driving to their final position. The pair left on the end then forms the support of the next panel along.
Another technique is to use trestles and walings to support and position sheet piles during driving.
Vibratory hammers are often used to install sheet piles, although if soils are too hard or dense, an impact hammer can be used. At certain sites where vibrations are a concern, the sheets can be hydraulically pushed into the ground.
[edit] Related articles on Designing Buildings
- All you need to know about sheet piling.
- Bored piles.
- Capping beam.
- Cofferdam.
- Continuous flight auger piles.
- Diaphragm wall.
- Driven piles.
- Groundwater control in urban areas.
- Groundworks.
- Micropiles.
- Pile cap.
- Pile foundations.
- Pile wall.
- Retaining walls.
- Screw pile foundations.
- Secant pile wall.
- Temporary works.
- Z piles.
- Types of pile foundation.
Featured articles and news
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description fron the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.


























Comments