Caisson
Contents |
[edit] Introduction
A caisson is a box-like structure commonly used in civil engineering projects where work is being carried out in areas submerged in water. Such projects might include:
- Bridge piers.
- Abutments in lakes and rivers.
- Break water and other shore protection works.
- Wharves and docks.
- Large water front structures.
Caissons differ from cofferdams in that cofferdams are removed after completion of the work, whereas caissons are built to remain in place as a part of the completed structure.
Caissons can be made of materials including timber, steel, masonry and reinforced concrete, and may be constructed onshore then floated to the required location, where they are sunk into place, enabling access to the bed and excavation of foundations to the required depth.
They are particularly suitable for the construction of underwater foundations or where the water is deep, as they are strong enough to withstand significant vertical and horizontal loads, as well as lateral forces such as waves.
[edit] Types of caisson
There are several different types of caisson, the choice of which will depend upon the structure for which it is being built as well as the required depth. Some of the more most common types are describes below:
[edit] Box caisson
This is a watertight timber or reinforced concrete box with a closed bottom and an open top. The caisson is cast and cured on land and then sunk into place, or it can be rested on top of a pile formation. Sand, concrete or gravel is used to weigh down and sink the caisson. This is most suitable for areas where the bearing strata is reasonably level and no excavation is required, although it is possible for some dredging to further level the base if required to avoid the tilting of the caisson once in place.
This type of caisson is generally relatively economical but may not be suitable if the bearing strata requires compacting and/or levelling.
[edit] Open caisson
This is a timber, steel or concrete box that is open at both the bottom and the top. The walls are heavy and made with sharp edges that facilitate the sinking process. There are three different types of open caisson:
[edit] Single wall
As opposed to box caissons which are prefabricated, open caissons are formed in situ. Wherever possible, a temporary cofferdam is constructed to keep the working environment dry and to enable the excavation of a pit in which the caisson is to be sunk, either by its self-weight, by concrete or by the use of hydraulic jacks if the skin friction prevents it from sinking. The soil from the space inside the caisson can then be removed by a clamshell excavator bucket on a crane.
The sinking proceeds at the rate necessary to allow each section to be concreted to a sufficient strength. Once sunk to the required depth, the base is plugged with a thick seal of concrete and once set the internal water is pumped out, to be replaced with sand, gravel or concrete.
[edit] Cylindrical (or well)
This is a cylindrical shell made of timber, masonry, steel or reinforced concrete. The wall must be sufficiently thick so that when the soil from inside is excavated, it sinks under its own weight. A cutting edge on the base of the walls and water jets can be used to assist sinking and reduce the level of skin friction. Once sunk to the required depth, the bottom is sealed with concrete.
[edit] Open with dredging wells
This method is commonly used for the deepest foundations, such as bridge piers and abutments. The outside walls, as well as inside divider walls which make up smaller sections (or wells), are made of reinforced concrete. Dredging the soil out through the wells enables the caisson to sink. Once sunk to the required depth, a concrete seal is installed and the walls filled with sand or concrete.
[edit] Pneumatic caisson
Pneumatic caissons are closed at the top but open at the bottom, with the water forced out using compressed air, creating a working chamber which is airtight in order for excavation to be carried out. This is suitable when it is not possible to excavate wet ground in the open.
To facilitate the internal work, the caisson has two air locks that consist of a steel chamber and two air-tight doors. One air lock allows labourers to enter and exit, and the other is used for removing the excavated material. It is important that the air pressure must be carefully monitored at all times, with slow raising and lowering as the labourers enter and leave the chamber. Otherwise, there is the risk of labourers suffering with caisson disease which results from the expansion of air bubbles trapped in joints and muscles.
Although this method is suitable for difficult locations, such as depths ranging from 25-40 m, it is a complex, slow and expensive procedure.
[edit] Related articles on Designing Buildings Wiki
- Bridge construction.
- Coastal defences.
- Cofferdam.
- Difference between cofferdams and caissons.
- Dredging.
- Driven piles.
- End-bearing piles.
- Formwork.
- Freezing method.
- Geothermal pile foundations.
- Groundwater control in urban areas.
- Grouting in civil engineering.
- Invert
- Micropiles.
- Piers.
- Pile foundations.
- Pumps and dewatering equipment.
- Retaining walls.
- River engineering.
- Scour.
- Screw piles.
- Secant pile wall.
- Socket piles.
- Temporary works.
- Tremie.
- Underpinning.
- Underwater foundations.
- Watercourse.
- Water engineering.
[edit] External references
- The Construction Civil - Types of caisson
- Best Engineering Projects - Caisson
Featured articles and news
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description fron the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
























