Construction contract conditions
Contract conditions set out the principal legal relationship between the parties to a construction project, determining the allocation of risk and consequently, price.
English law, unlike the codified legal systems in Europe which recognise a duty of good faith, is not concerned with fairness but with certainty (unless it is a consumer contract protected by statute such as the Consumer Protection Act 1987 or the Unfair Contract Terms Act 1977).
The construction sector has a wide range of standard forms of contract which are intended to balance the risk of the parties but more importantly, through extensive and repeated use, give rise to a certainty of meaning. Well-known standard form contracts include the Joint Contracts Tribunal (JCT), the New Engineering Contract (NEC) and for international projects Fédération Internationale des Ingénieurs-Conseil (FIDIC).
See the article on Contracts for more information.
Standard form contracts also provide for different procurement routes, such as:
- Construction management.
- Design and build.
- Design build finance and operate (PPP / PFI / DBO / BOOT).
- Emerging cost contracts.
- Engineering Procurement and Construction Contract (EPC) / Turnkey contract
- Engineering Procurement and Construction Management contract (EPCM)
- Furniture, Fixtures and Equipment contract (FF&E).
- Framework agreements.
- Management contract.
- Measured term contracts
- Measurement contract ('re-measurement' or ‘measure and value’ contract)
- Partnering.
- Prime cost contract / cost plus contract / cost reimbursable contract
- Prime contracting / prime-type contracting
- Traditional contract.
See the article on Procurement routes for more information.
Typical conditions found in construction contracts can include (in alphabetical order):
- Access to the construction site.
- Assignment, rights of third parties and collateral warranties.
- Commissioning.
- Contractor's design.
- Contract sum and adjustment,
- Date for possession, deferment of possession, progress, delays, completion date, suspension of works and termination.
- Dispute resolution procedures and alternative dispute resolution.
- Employer's instructions.
- Force majeure.
- Information release schedule.
- Insolvency.
- Injury, damage and insurance.
- Joint Fire Code.
- Liquidated damages.
- Net contribution clause.
- Partial possession.
- Payment, valuation (including off-site materials), certificates, fluctuations and retention.
- Practical completion.
- Project management and contract administration.
- Quality of works.
- Relevant events (compensation events), extensions of time and loss and expense.
- Sectional completion.
- Statutory obligations.
- Sub-contractors.
- Testing and defects (defects liability period)
- Variations, prime cost sums and provisional sums.
Conditions of contract must be read in conjunction with specification documents, drawings bills of quantities, activity schedules and special conditions. Standard form contracts often comprise suites of contracts with ‘back to back’ subcontracts, consultant appointments and collateral warranties. The use of core conditions with option schedules or supplemental provisions is also now common (see NEC contract).
[edit] Related articles on Designing Buildings
- Addendum.
- Alternative dispute resolution.
- Articles of agreement.
- Common law.
- Competitive procedure with negotiation.
- Condition.
- Construction contract.
- Construction law.
- Contract administrator.
- Contract negotiations.
- Contract strategy.
- Contractual right.
- Delay damages.
- Disallowed cost.
- Escalation.
- Essentials of a contract.
- Excepted risk.
- Extension of time.
- Form of tender.
- Hybrid construction contract.
- Key dates.
- Liquidated damages.
- Loss and expense.
- Modifying clauses in standard forms of contract.
- Named specialist work.
- Negotiated Procedure without Prior Publication NPwPP.
- Outturn cost.
- Payment for extra work.
- Pre-contract management.
- Proprietary information.
- Quantum meruit.
- Right to payment.
- Supply chain management.
- Variation.
- Z clauses.
Featured articles and news
A transformative shift in the design, construction and management of built assets.
Apprenticeship announcement by the Prime Minister
Welcomed but with call for more actionable detail.
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach 7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Comments
this site is indeed very informative👍 worth to spend sometime reading during work break