Pre-contract management
In the construction industry, contract management is the process of managing contracts that are made as part of the delivery of a built asset. It involves the creation, analysis and execution of contracts by the parties to those contracts to ensure operational and financial performance is maximised, and risks are minimised.
Contract management can categorised into three phases:
- Pre-contract phase.
- Contract execution phase.
- Post-award phase.
The pre-contract phase is the preparation stage. This is when ideas start to form about the project and it is described in theoretical terms. It is also when intentions are solidified and relationships begin to take shape.
Although each scenario may be different, these are some of the typical steps that may be included in the pre-contract stage.
- Survey phase. This is when the project team starts to collect survey information for the project. It may include contributions and basic options from all consultants regarding the feasibility of the project. This information can start to form a design brief around ideas provided by the client.
- Outline phase. At this point, the project team creates a concept based on the design brief requirements and provides an outline that includes input from relevant parties and authorities.
- Scheme design. This phase is when the project team shapes the agreed upon idea into a working proposition including approvals from applicable authorities.
- Detail design. During this phase, the project team has fully developed the idea for the project, including specialist design work for structures, electrical, plumbing and HVAC installations and other required services that will be provided by sub-contractors..
- Construction information. At this point, the project team prepares detailed working drawings and specifications that define all aspects of the project.
- Measurement. The project team will prepare the bill of quantities including measurements for materials and estimates of labour costs for the project.
- Tendering. This is when tender documents are prepared, tenders are sought from selected contractors and contract negotiation is undertaken.
Once these phases are complete, there is an analysis of tenders that ideally concludes with the client awarding the project to the successful contractor based on the approved design, strategy and documentation.
[edit] Related articles on Designing Buildings
Featured articles and news
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Update on the future of Grenfell Tower
Deputy Prime Minister decides for it be carefully taken down to the ground.
Ending decades of frustration, misinformation and distrust.
Essential tools in managing historically significant landscapes.
Classroom electrician courses a 'waste of money'
Say experts from the Electrical Contractors’ Association.
Wellbeing in Buildings TG 10/2025
BSRIA topic guide updates.
With brief background and WELL v2™.
From studies, to books to a new project, with founder Emma Walshaw.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.