Pre-contract management
In the construction industry, contract management is the process of managing contracts that are made as part of the delivery of a built asset. It involves the creation, analysis and execution of contracts by the parties to those contracts to ensure operational and financial performance is maximised, and risks are minimised.
Contract management can categorised into three phases:
- Pre-contract phase.
- Contract execution phase.
- Post-award phase.
The pre-contract phase is the preparation stage. This is when ideas start to form about the project and it is described in theoretical terms. It is also when intentions are solidified and relationships begin to take shape.
Although each scenario may be different, these are some of the typical steps that may be included in the pre-contract stage.
- Survey phase. This is when the project team starts to collect survey information for the project. It may include contributions and basic options from all consultants regarding the feasibility of the project. This information can start to form a design brief around ideas provided by the client.
- Outline phase. At this point, the project team creates a concept based on the design brief requirements and provides an outline that includes input from relevant parties and authorities.
- Scheme design. This phase is when the project team shapes the agreed upon idea into a working proposition including approvals from applicable authorities.
- Detail design. During this phase, the project team has fully developed the idea for the project, including specialist design work for structures, electrical, plumbing and HVAC installations and other required services that will be provided by sub-contractors..
- Construction information. At this point, the project team prepares detailed working drawings and specifications that define all aspects of the project.
- Measurement. The project team will prepare the bill of quantities including measurements for materials and estimates of labour costs for the project.
- Tendering. This is when tender documents are prepared, tenders are sought from selected contractors and contract negotiation is undertaken.
Once these phases are complete, there is an analysis of tenders that ideally concludes with the client awarding the project to the successful contractor based on the approved design, strategy and documentation.
[edit] Related articles on Designing Buildings
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.