Working drawing
Contents |
[edit] What is production information?
Production information is '...the information prepared by designers, which is passed to a construction team to enable a project to be constructed' (ref. CPIC The importance of production information). Production information is incorporated into tender documentation and then the contract documents for the construction works.
Production information may include:
- Drawings, such as working drawings.
- Specifications.
- Bills of quantities or schedules of work.
[edit] What are working drawings?
Working drawings provide dimensioned, graphical information that can be used; by a contractor to construct the works, or by suppliers to fabricate components of the works or to assemble or instal components. They may include architectural drawings, structural drawings, civil engineering drawings, mechanical drawings, electrical drawings, and so on.
Traditional working drawings consist of two-dimensional orthogonal projections of the building or component they are describing, such as plans, sections and elevations. These may be drawn to scale by hand, or prepared using Computer Aided Design (CAD) software.
However, increasingly, building information modelling (BIM) is being used to create three-dimensional representations of buildings and their components for construction. This may be described as a virtual construction model (VCM) and can comprise a number of different models prepared by different members of the project team.
NB Roles in construction projects: analysis and terminology, by Hughes, W. and Murdoch, J. R, published in 2001 by the University of Reading, suggests that working drawings is: ‘A term that used to be common but seems to have fallen into disuse, describing information produced by designers for builders.’
[edit] How should working drawings be prepared?
Working drawings may include title blocks, dimensions, notation and symbols. It is important that these are consistent with industry standards so that their precise meaning is clear and can be understood. Specification information can be included on working drawings or in a separate specification, but information should not be duplicated as this can become contradictory and may cause confusion.
The scale at which drawings are prepared should reflect the level of detail of the information they are required to convey. Different line thicknesses can also be used to provide greater clarity for certain elements.
It is important that the purpose of the drawings and the people that will use them are considered. Working drawings might be prepared for; statutory approvals, for contractors to plan the construction works, to provide instructions on site, for the procurement of components, for the preparation of shop drawings, for the appointment of subcontractors and so on.
Drawings must be structured carefully so that they convey necessary information to carry out particular parts of the works. To give greater clarity, they may be separated into packages, so that information is specifically tailored to separate parts of the works, specific components, or separate suppliers or trades.
It may be necessary to produce some packages earlier than others, for example, for items with long manufacturing times such as switchgear, chiller units, lifts, escalators or bespoke cladding systems, or for front-end construction such as service diversions, demolition, setting out details, underground drainage, piling and groundworks.
Working drawings may be updated when the works are complete to show ‘as constructed’ information, reflecting changes to the works that may have occurred during the construction process.
The quality of working drawings is extremely important. Unless it is prepared and co-ordinated properly, there will be disputes and delays on site, and costs will be incurred. Common problems with working drawings include:
- Poor co-ordination of information.
- Errors and omissions.
- Information not getting to the right people.
- Poor presentation.
- Using out of date information.
Carefully prepared working drawings can be very beautiful and the very best have been exhibited as works of art.
[edit] Who prepares working drawings?
Responsibility for the preparation of working drawings will depend on the selected system of procurement and the chosen form of contract. On traditional contracts (and management contracts and construction management contracts), working drawings may be produced by a consultant team, working for the client.
Some specialist elements of working drawings may be produced by specialist contractors, co-ordinated by the lead designer. On other forms of contract, such as design and build, responsibility for preparing and co-ordinating working drawings may lie with the main contractor.
[edit] Related articles on Designing Buildings
- As-built drawings and record drawings.
- Assembly drawing.
- Building information modelling.
- Common mistakes on building drawings.
- Computer aided design.
- Design drawings.
- Detail drawing.
- Drawings.
- Engineering drawing.
- Installation drawings.
- Notation and symbols.
- Production information.
- Projections.
- Scale drawing.
- Shop drawings.
- Technical drawing.
- Technical drawing pen sizes.
- Techniques for drawing buildings.
- Types of drawing.
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
What scales are used for working drawings?
It depends what the drawings are of and what level of detail is required.