Contract documents for construction
See also Contractual documents for a list of documents that are commonly required by or referred to in a construction contract.
Contents |
[edit] Traditional contract
The contract documents set out the obligations and responsibilities of the parties to the contract. On a traditionally-procured, fully-designed construction project, the contract documents for suppliers such as the main contractor are likely to include:
- Article of agreement and conditions of contract, for completing as a simple contract (or as a deed).
- Working drawings.
- Bills of quantities.
- Specifications.
- Schedules of work.
- Perhaps an information release schedule. Consultants can be reluctant to produce information release schedules because of concerns about being held to the dates on the schedule (even where the progress of construction does not require information when the information release schedule proposes it). Failure to keep to the dates set out in the information release schedule may then be a matter for which the contractor can claim an extension of time and loss and/or expense.
- A schedule of tender adjustments or clarifications negotiated and agreed after the receipt of tenders and prior to the signing of the contract.
- The requirement for the contractor to provide a performance bond and to obtain collateral warranties from any sub-contractors or suppliers.
Both client and contractor should engross the contract by witnessed signatures prior to commencement of work. In practice the administrative effort of collating all necessary paperwork can be overtaken by the desire to begin construction. In such circumstances it becomes harder to sort out any disputes as to the content. There have been cases where the courts have had to interpret an implied contract when the contract has remained unsigned.
[edit] Design and build
On design and build projects, the contract documents may comprise:
- The articles of agreement and conditions of contract.
- The employer's requirements.
- The contractor's proposals.
- The contract sum analysis.
- Possibly bills of quantities (for some or all of the design).
[edit] Building information modelling
On projects that adopt building information modelling (BIM), the contract documents may also include:
- A model enabling amendment introducing a BIM protocol as part of the contract documents.
- A BIM protocol, which establishes specific obligations, liabilities and limitations on the use of building information models and can be used by clients to mandate particular working practices.
- Employer's information requirements, which define information that the employer wishes to procure to ensure that the design is developed in accordance with their needs and that they are able to operate the completed development effectively and efficiently. Suppliers respond to the employer's information requirements with a BIM execution plan.
Click here to see a diagram showing the relationship between contractual documents for BIM.
[edit] NEC3
The contract documentation under NEC contracts comprises:
- The form of agreement.
- Conditions of contract.
- Contract data.
- Prices, activities schedules, bill of quantities.
- Works information.
- Site information.
[edit] Pre-contract meeting
A pre-contract meeting is likely to take place after the contractor has been appointed. This is an opportunity to for the project team to meet (perhaps for the first time) and to plan their activities. The minutes of the pre-contract meeting may form part of contract documents (for all procurement routes) subject to the agreement of both parties.
[edit] Related articles on Designing Buildings
- Articles of agreement.
- Association of Consultant Architects TAC-1 launch and BIM
- Bills of quantities.
- Boilerplate.
- Conformed contract.
- Construction contract.
- Contract conditions.
- Contract engrossment.
- Contract execution.
- Contract negotiation.
- Contract notice.
- Contractual documents.
- Contractors proposals.
- Contract sum analysis.
- Employers requirements.
- Engrossment.
- Form of tender.
- Information release schedule.
- Manual of Contract Documents for Highway Works.
- Named specialist work.
- Performance bond.
- Pre-contract meeting.
- Prescriptive specification.
- Procurement route.
- Schedules of work.
- Smart contracts.
- Specifications.
- Supply contract.
- Tender.
- Tender documents.
- Working drawing.
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.
Comments