Contractual documents
This article lists the documents that are commonly required by or referred to in a construction contract. See also Contract documents for a list of the documents setting out the obligations and responsibilities of the parties to the contract on a traditionally-procured, fully-designed construction project,
In some cases, different contracts may use different names for the same document. Where this is the case, alternative names are shown.
- Application for payment (see Fair payment practices)
- Architect's instruction / contract administrator's instruction
- Bill of quantities
- Building log book
- Building owner's manual / operation and maintenance manual (O&M manual)
- Building users guide
- Certificate of making good defects / certificate of making good
- Collateral warranty
- Construction phase plan
- Contract sum analysis
- Contractors master programme
- Contractors proposals
- Default payment notice (see Fair payment practices)
- Contract drawings
- Design documents
- Employers requirements
- Final account
- Final certificate
- Health and safety file
- Information release schedule
- Insurance
- Interim certificate
- Joint fire code
- Method statement
- Pay less notice (see Fair payment practices)
- Payment notice (see Fair payment practices)
- Practical completion certificate / substantial completion certificate
- Preliminaries
- Risk assessment
- Schedule of defects
- Schedule of work
- Site waste management plan
- Specification
NB: A pre-contract meeting is likely to take place after the contractor has been appointed but before work commences on site. This is an opportunity to for the project team to meet (perhaps for the first time) and to plan the construction stage. The minutes of the pre-contract meeting may form part of contract documents (for all procurement routes) subject to the agreement of both parties.
See Pre-contract meeting for more information.
[edit] Related articles on Designing Buildings Wiki
- Bills of quantities.
- Construction contract.
- Contract conditions.
- Contract documents.
- Contractors proposals.
- Contract sum analysis.
- Employers requirements.
- Form of tender.
- Information release schedule.
- Performance bond.
- Pre-contract meeting.
- Procurement route.
- Schedules of work.
- Specifications.
- Tender.
- Tender documents.
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.