Building owner's manual - O and M manual
The building owner's manual, or operation and maintenance manual (O&M manual), contains the information required for the operation, maintenance, decommissioning and demolition of a building.
The building owner's manual is prepared by the contractor or the sub-contractor with additional information from the designers (in particular, the services engineer) and suppliers. It is a requirement that is generally defined in the preliminaries section of the tender documentation where its contents will be described, although there may be additional requirements regarding mechanical and electrical services in the mechanical and electrical specification.
A draft version of the document should be provided for the client as part of the handover procedure prior to certifying practical completion. The final document is not usually available in full form until several months after practical completion, as commissioning information often needs to include summer and winter readings taken in the fully occupied building. The preliminaries may require several copies of the building owner's manual and might require an electronic version.
The building owner's manual might include:
- A description of the main design principles.
- Details of the building's construction (such as finishes, cladding, doors and windows, roof construction, and so on).
- As-built drawings and specifications.
- Instructions for its operation and maintenance (including health and safety information and manufacturers' instructions for efficient and proper operation).
- An asset register of plant and equipment.
- Commissioning and testing results.
- Guarantees, warranties and certificates.
- Particular requirements for demolition, decommissioning and disposal.
Much of this information will already exist in one form or another, so preparing the building owner's manual might simply be a matter of compiling and assembling its components.
Over the life of the buildings, the building owner's manual may be developed to reflect changes that take place to the fabric of the building or its systems, along with details of maintenance that has taken place .
The building owner's manual is different from the health and safety file which only needs to include information important to health and safety and does not need to include information about the construction process, contractual information or information about the normal operation of the completed structure.
The building owner's manual may also include a non-technical 'building user's guide' with information for users about environmental controls, access, security and safety systems, etc.
NB - Building owner's manuals might now be referred to as building manuals. For more information see: Building manual.
[edit] Related articles on Designing Buildings
- BSRIA updates Handover and O&M manuals.
- Building log book.
- Building manual.
- Building user's guide.
- Decommissioning.
- Deferred maintenance.
- End-user.
- Handover to client.
- Health and safety file.
- Maintenance.
- Operation, maintenance and training (OMT).
- Practical completion.
- Preliminaries.
- Soft Landings for owners.
- Technical guide.
- Tender documentation.
- Users.
- Working with maintenance contractors.
[edit] External references
- BSRIA Handover, O&M Manuals, and Project Feedback. A toolkit for designers and contractors (BG 1/2007).
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments