Construction contract certificates, notices and instructions
Contents |
[edit] Certificates
Many standard forms of construction contract require that certificates are issued by the contract administrator. Certificates generally result in payment being made by the client to the contractor. These certificates can either be issued regularly during the course of the works, such as interim certificates (normally issued monthly), or may signify that a particular stage has been achieved, such as practical completion. This can trigger other transitions, such as the commencement of a lease or access for a tenant to commence tenant works.
Typically, the certificates issued under a construction contract will include:
- Interim certificates.
- Certificate of practical completion (or section completion certificates where the works are to be completed in sections).
- Certificate of making good defects.
- Certificate of non-completion.
- Final certificate.
- There may also testing certificates for works and activities such as commissioning, electrical work, sprinkler systems, building regulations, concrete cube crushing, cladding mock ups and so on.
The Housing Grants, Construction and Regeneration Act 1996 (also known as the Construction Act) provides for the right to be paid in interim, periodic or stage payments, as well as the right to suspend (or part suspend) performance for non-payment and to claim costs and expenses incurred and extension of time resulting from the suspension. In addition, the Act requires that if the client intends to pay less than the amount certified they must issue a pay less notice setting out the basis for their calculation. Care must be taken to certify the correct amount, as over-certification followed by insolvency of the contractor may result in the client making a claim for negligent certification against the contract administrator.
Other specific certificates may be required (some from third parties) on completion of different aspects of the works:
- Fire regulation compliance.
- Electrical completion certificates.
- Test certificates both for manufacturing and installation.
- Lifting beams tests and marking.
- Building regulation compliance.
- Pressure vessel and boiler certificates.
Particular licenses and certificates may also be required for specialist projects, such as nuclear, pharmaceutical, oil, gas, and rail projects.
For more informtion see: Certificates.
[edit] Notices
Construction contracts also often include requirements for the parties to issue notices to each other under certain circumstances. This is often intended to provide a warning mechanism, enabling the parties to prepare for, or react to, particular situations. The contract should make clear the circumstances under which a notice is required, the form of the notice, the information it should contain, who it should be sent to, at what address and the notice period. Failure to follow the correct procedure can result in a subsequent claim being defeated.
Notices (or in some cases statements) might include:
- Default payment notice.
- Notification of failure to proceed regularly and diligently.
- Notice that there is a delay, or that there is likely to be a delay that could merit an extension of time.
- Notice of intention to refer a dispute to an adjudicator.
- Notice to proceed.
- Notification of an extension of time.
- Pay less notice.
- Payment notice.
- Statement of partial possession.
- Statement of retention.
- Suspension notice.
- Termination notice.
For more information see: Notices.
[edit] Instructions
Construction contracts will also generally give the contract administrator the power to issue instructions to the contractor. Broadly, instructions may be given:
- To vary the works.
- To postpone the works.
- To remedy workmanship, goods or materials which are not in accordance with the contract.
- To sanction a variation made by the contractor.
- In relation to the expenditure of provisional sums.
- To open up work for inspection.
- To carry out tests.
- To exclude persons from the site.
[edit] Related articles on Designing Buildings Wiki
- Architects instructions.
- Certificate of making good defects.
- Certificate of practical completion.
- Certificates in the construction industry.
- Confirmation of verbal instruction.
- Contractual right.
- Interim certificate.
- Final certificate.
- Off site materials.
- Payment notices.
- Permit.
- Sectional completion.
- The Construction Act.
- Termination.
- Variations.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Rethinking passive fire protection in design
PFP demands the same level of design rigour as structure or services.
38% of Gen Zs feel safe when a fire door is wedged open.
Stunning images from around the world
Shortlist for CIOB’s Art of Building photography competition.
Guidance for conversion of traditional pre-1919 stone buildings.
Industrial heritage in the Ruhr
A marked difference to the fate of industrial landscapes in the UK.
Communities will be able to build their own clean energy.
Why diversity and inclusion matters for SMEs
CIOB’s D&I Charter shows how practical changes can support long-term growth.
Cut electricity bills to power growth
Coalition sends joint letter to the Chancellor.
Gasholders: a history in pictures. Book review.
Recognition, influence and growth
SocEnv identifies three strategic pillars in new strategy to 2045.
Discover the future of roofing, cladding and insulation.
New guidance for professional practice, cultural change and regulation in social housing.


















Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.