Third party dependencies for building design and construction
Not every aspect of a project is within the direct control of the client or their project team. Every project is dependent to some extent on third parties. It is important that these third party dependencies are identified and that their potential impacts are understood, quantified and managed.
Third parties may not be motivated by the same objectives as the client or project team, but nevertheless they can have a serious impact on the programme for a project. It is not safe to assume, just because a time allocation has been made within a programme for a third party dependency, that the third party has any interest in keeping to that programme.
These third parties are often different from stakeholders in that they may have no interest in the project or any ability to affect decisions, and yet they may still be in a position to impact upon success.
Third parties can even be responsible for completely unrelated, circumstantial dependencies, such as the legislative framework. For example, the introduction of changes to the building regulations can have a very significant impact on a project and yet are entirely beyond the control of the project team.
The range of potential third party dependencies is very wide and will vary from project to project, but may include:
- Neighbours (planning matters, party wall matters, access and other permissions, easements, right to light, tree rights and so on).
- Licensing authorities.
- Planning authorities.
- Building control.
- Other statutory authorities and non-statutory authorities (Health and Safety Executive, Environment Agency, Civil Aviation Authority, English Nature, Historic England, CABE, Highways England and so on – see Statutory authorities for more information).
- Utilities companies and other statutory undertakers.
- Purchasers or vendors of land or properties.
- Archaeological or other surveyors (surveys can reveal issues such as; archaeological remains, unexploded bombs, asbestos, contamination, japanese knotweed, roosting bats, great crested newts, tree preservation orders and so on that can cause very significant delays to a project).
- Dependent projects (for example decontamination of the site by a third party prior to sale of land to the client).
- Funding availability.
- Local Chambers of Commerce.
- Politicians.
- Competitors.
- The supply market (goods, labour, plant, equipment and so on).
- Unions.
- The availability of third party services (such as local schools, feeder organisatons, local transport, local infrastructure and so on.)
- The political and legislative framework.
- The wider economic context.
- Customers.
- Emergency services.
- Community groups.
- Special interest groups.
- The press.
Identifying and assessing these third party dependencies should involve the whole project team, and can be best carried out at a project workshop (for example it may form part of a risk workshop – see risk register for more information). Techniques such as PEST analysis (Political, Economic, Social, Technological) can help identify third party dependencies.
It is important that this is not simply a paper exercise. The probability and importance of impacts should be assessed so that resources can be prioritised, responsibilities allocated and strategies put in place to monitor progress (see stakeholder and stakeholder map for more information about how this might be done).
Where risks remain, strategies should be put in place to mitigate, transfer, avoid or accept those risks. See risk register for more information.
[edit] Related articles on Designing Buildings Wiki
- BREEAM independent party.
- Collaborative practices.
- Consultation process.
- Dependency.
- Early BREEAM stakeholder engagement.
- Externalities.
- Independent third party.
- Interested party.
- Receptor.
- Risk management.
- Risk register.
- Stakeholders.
- Stakeholder management: a quality perspective.
- Stakeholder map.
- Statutory authorities.
- Statutory undertakers.
- Technical due diligence.
- Utilities.
Featured articles and news
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.