Construction activities
An activity is an operation or process consuming time and possibly other resources. An individual or work team can manage an activity. It is a measurable element of the total project programme.
The term ‘duration’ refers to the length of time needed to complete an activity.
The term 'path' refers to an activity or an unbroken sequence of activities in a project network. The critical path is the longest sequence of activities through a project network from start to finish, the sum of whose durations determines the overall project duration.
‘Float’ is the time available for an activity in addition to its planned duration. For more information see: Programme float.
‘Free float’ is the amount of time that an activity can be delayed beyond its early start/early finish dates without delaying the early start or early finish of any immediately following activity.
A hanging activity is an activity not linked to any preceding or successor activities.
'Impact' is the effect a change has on an activity or the effect a change to one activity has
on another activity.
Ref Society of Construction Law Delay and Disruption Protocol, 2nd edition, February 2017, published by the Society of Construction Law (UK). https://www.scl.org.uk/resources/delay-disruption-protocol
Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests that: ‘…Each work package comprises a number of activities to be performed. Each activity can be assigned to only a single work package. Each activity is a stepping stone towards completion of its parent work package.’
NB The CIOB Planning Protocol 2021 (CIOB PP21), a technical information sheet published by the Chartered Institute of Building (CIOB) in February 2021, defines an activity as: ‘A definable and measurable unit of work. Each activity has a start date, an end date and a duration.’
The glossary of statistical terms, published by the Organisation for Economic Co-operation and Development (OECD), states: ‘An activity is a process, i.e. the combination of actions that result in a certain set of products.’
[edit] Related articles on Designing Buildings
Featured articles and news
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach £7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
How to write an inspection and test plan
ITPs for quality control and assurance particular elements.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Winners of the 2024 ASBP Awards
Project, Product and Initiative according to the 6 pillars.