Disruption claims in construction
In construction contracts, the term 'disruption' refers to a loss of productivity due to a hindrance or interruption of the progress of the construction works which reduces the rate of efficiency.
If disruption is caused by the employer, the contractor may have grounds to seek compensation. Disruption, and claims arising to try and recoup losses incurred from it, are common on construction projects, particularly on larger and more complex projects.
The difference between disruption and delay is that the latter relates to lateness rather than productivity, although they can often be related. Delays can cause disruptions, and vice versa. Despite their inter-relation, they require a different approach to assessing claims.
When evaluating claims for delay, the terms of the specific contract are the usual starting point, and evidence is required that certain circumstances caused the delay. The terms of the contract are less useful when evaluating disruption claims. Instead, the contractor must provide reasonable evidence that:
- Progress of the works has been disrupted.
- Which element of the works and which trades have been disrupted, why losses occurred, and so on.
- The disruption incurred additional costs.
- The cause of the disruption constitutes a breach of contract.
Evidence will normally take the form of documented records demonstrating that disruption caused losses. However, this can prove difficult as the contractor can often not detect disruption until after it has occurred. In addition, isolating the loss of productivity to the cause of the disruption can be difficult as it may coincide with several other factors, and the effect of the disruption may be hidden by other issues.
Several methods can be used to estimate loss in relation to disruption, including:
- Measured mile analysis: Compares actual labour performance between two periods – a normal measured mile period and an impacted period.
- Baseline productivity analysis: A more conservative estimate used when an unimpacted section of the works is too difficult to isolate.
- Earned value analysis: Compares the amount and cost of work that was planned to have been done by a particular stage with the amount that has actually been done and what it has actually cost.
NB The term ‘disruption’ can also refer to the impact of new technologies and techniques on an industry. For more information, see Construction is an industry ripe for tech disruption.
Anticipate, react, recover; Resilient infrastructure systems, published by the National Infrastructure Commission in May 2020, defines disruption as: ‘A disturbance which interrupts the usual functioning of an infrastructure system or service, and its impacts.’
[edit] Related articles on Designing Buildings
Featured articles and news
Professional practical experience for Architects in training
The long process to transform the nature of education and professional practical experience in the Architecture profession following recent reports.
A people-first approach to retrofit
Moving away from the destructive paradigm of fabric-first.
International Electrician Day, 10 June 2025
Celebrating the role of electrical engineers from André-Marie Amperè, today and for the future.
New guide for clients launched at Houses of Parliament
'There has never been a more important time for clients to step up and ...ask the right questions'
The impact of recycled slate tiles
Innovation across the decades.
EPC changes for existing buildings
Changes and their context as the new RdSAP methodology comes into use from 15 June.
Skills England publishes Sector skills needs assessments
Priority areas relating to the built environment highlighted and described in brief.
BSRIA HVAC Market Watch - May 2025 Edition
Heat Pump Market Outlook: Policy, Performance & Refrigerant Trends for 2025–2028.
Committing to EDI in construction with CIOB
Built Environment professional bodies deepen commitment to EDI with two new signatories: CIAT and CICES.
Government Grenfell progress report at a glance
Line by line recomendation overview, with links to more details.
An engaging and lively review of his professional life.
Sustainable heating for listed buildings
A problem that needs to be approached intelligently.
50th Golden anniversary ECA Edmundson apprentice award
Deadline for entries has been extended to Friday 27 June, so don't miss out!
CIAT at the London Festival of Architecture
Designing for Everyone: Breaking Barriers in Inclusive Architecture.
Mixed reactions to apprenticeship and skills reform 2025
A 'welcome shift' for some and a 'backwards step' for others.