Earned value for construction contracts
|
Earned value analysis (EVA), also known as earned value management (EVM), is a technique used to assess project progress by comparing the amount and cost of work that was planned to have been done by a particular stage with the amount that has actually been done and what it has actually cost.
This gives a good indication of how the project is progressing compared to what was planned and enables forecasts to be made about the eventual cost and time that will be required to complete the project.
Typically, EVA is carried out for each of the packages that make up the project. Actual outputs are measured against planned outputs (often on a weekly basis) using the units that individual companies use to price and measure work.
This provides an opportunity to investigate discrepancies and take remedial action where necessary. It also provides a fairly accurate insight into the financial wellbeing of package contractors and provides early warning of a shortage of resources or of an inefficient use of resources.
The key is to measure actual resource against planned resource using the production units by which estimates have been produced in order to price a tender. This can be:
- Hours worked per week.
- Number of workers per week.
- Volume of say, concrete per week per person.
- Units fixed per week per person.
These items can be plotted weekly to alert the user to trends and allow them to investigate causes. Furthermore, it provides an overall general picture of labour productivity for each monitored operation.
Carrying out this sort of analysis requires that project planning is broken down into packages and that tender documentation is drafted to require contractors to supply the information required.
[edit] Related articles on Designing Buildings Wiki
- Benchmarking.
- Contractor.
- Cost monitoring.
- Cost performance index (CPI).
- Identifying the causes of trends in construction labour productivity.
- Key performance indicators.
- Programme consultant.
- Progress of construction works.
- Schedule performance index (SPI).
- Sub-contractor.
- Tender.
- Tender documentation.
[edit] External references
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.
The adaptive reuse of large industrial structures.
Promoting the circular economy by extending the life of buildings.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.
Construction Management, 17 June
Government rolls out digital planning tool to all local authorities.