Progress of construction works
Most construction contracts will include a date by which the works described in the contract must be completed. This is either by means of a defined completion date, or a commencement date and a specified period for the works. This date may be varied during the works, for example if an extension of time is granted, or if the works are accelerated.
If no date or period is defined, a term will be implied that the contractor must complete the works in a reasonable time, that is, the time it would ordinarily take, plus an allowance for any extraordinary circumstances.
Unless the contract includes express provisions requiring that the works are carried out in a particular way, the contractor can achieve the completion date in whatever manner they choose, for example, by starting slowly and then speeding up, or by working sporadically. There is no implied term requiring that the works are carried out to a specific timetable.
However, many contracts include express terms requiring that the contractor proceeds ‘regularly and diligently’ with the works, irrespective of whether they are likely to achieve the completion date. They cannot work sporadically, or slow down if it becomes apparent that they will beat the completion date. Sub-contracts may include similar obligations, requiring sub-contractor progress to be reasonably in accordance with the progress of the main contract.
The term ‘time at large’ refers to a situation in which there is no date for completion, or where the date for completion has become invalid. The contractor is then no longer bound by the obligation to complete the works by a certain date. They may however still be bound by an obligation to proceed regularly and diligently or to complete the works within a reasonable time.
Designing Buildings Wiki includes a number of articles providing more information about construction progress and its measurement:
- Acceleration.
- Accepted programme.
- Activity schedule.
- Base date.
- Benchmarking.
- Completion date.
- Construction progress meeting.
- Construction progress report.
- Contractor's master programme.
- Critical path method.
- Design programme.
- Earned value analysis.
- Extension of time.
- Fast track construction.
- Gantt chart.
- How progress is agreed in construction.
- Information release schedules.
- Key performance indicators.
- Lead time.
- Line of balance (LOB).
- Logistics management.
- Milestones.
- Pareto analysis.
- Phased construction works.
- Precedence diagram method.
- Productivity in building design and construction.
- Productivity in construction: Creating a framework for the industry to thrive.
- Programme consultant.
- Programme float.
- Programme for building design and construction.
- Project programme.
- Regularly and diligently.
- Scheduling construction activities.
- Short period programme.
- Tender works programme.
- Time-location chart.
- Time at large.
- Time is of the essence.
- Time management of construction projects.
[edit]
Featured articles and news
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.




















