Progress of construction works
Most construction contracts will include a date by which the works described in the contract must be completed. This is either by means of a defined completion date, or a commencement date and a specified period for the works. This date may be varied during the works, for example if an extension of time is granted, or if the works are accelerated.
If no date or period is defined, a term will be implied that the contractor must complete the works in a reasonable time, that is, the time it would ordinarily take, plus an allowance for any extraordinary circumstances.
Unless the contract includes express provisions requiring that the works are carried out in a particular way, the contractor can achieve the completion date in whatever manner they choose, for example, by starting slowly and then speeding up, or by working sporadically. There is no implied term requiring that the works are carried out to a specific timetable.
However, many contracts include express terms requiring that the contractor proceeds ‘regularly and diligently’ with the works, irrespective of whether they are likely to achieve the completion date. They cannot work sporadically, or slow down if it becomes apparent that they will beat the completion date. Sub-contracts may include similar obligations, requiring sub-contractor progress to be reasonably in accordance with the progress of the main contract.
The term ‘time at large’ refers to a situation in which there is no date for completion, or where the date for completion has become invalid. The contractor is then no longer bound by the obligation to complete the works by a certain date. They may however still be bound by an obligation to proceed regularly and diligently or to complete the works within a reasonable time.
Designing Buildings Wiki includes a number of articles providing more information about construction progress and its measurement:
- Acceleration.
- Accepted programme.
- Activity schedule.
- Base date.
- Benchmarking.
- Completion date.
- Construction progress meeting.
- Construction progress report.
- Contractor's master programme.
- Critical path method.
- Design programme.
- Earned value analysis.
- Extension of time.
- Fast track construction.
- Gantt chart.
- How progress is agreed in construction.
- Information release schedules.
- Key performance indicators.
- Lead time.
- Line of balance (LOB).
- Logistics management.
- Milestones.
- Pareto analysis.
- Phased construction works.
- Precedence diagram method.
- Productivity in building design and construction.
- Productivity in construction: Creating a framework for the industry to thrive.
- Programme consultant.
- Programme float.
- Programme for building design and construction.
- Project programme.
- Regularly and diligently.
- Scheduling construction activities.
- Short period programme.
- Tender works programme.
- Time-location chart.
- Time at large.
- Time is of the essence.
- Time management of construction projects.
[edit]
Featured articles and news
AI and the challenges to intellectual property
The legal landscape of adopting AI now and in the future.
Worrying landscape for Welsh construction SMEs revealed.
In recent risk factor analysis report completed by CIOB.
Construction Sport survey highlights risks of dehydration
Supporting construction workers to avoid dangers.
Can your business afford to ignore mental well-being?
£70 - 100 billion annually in UK construction sector.
Mental health in the construction industry
World Mental Health Day 10 October.
Construction awards provide relief in wake of ISG collapse
Spike in major infrastructure awards, housing up but short of targets, are ISG collapse impacts yet to come.
Biodiversity net gain with related updates and terms
Only 0.5% of applications subject to BNG in the context significant proposed changes to planning.
As political power has shifted from blue to red
Has planning now moved from brown to green?
The role of construction in tackling the biodiversity crisis
New CIOB Nature of Building digital series available now.
The Nature Towns and Cities initiative
Grants of up to 1 million for local councils and partners.
The continued ISG fall out October updates
Where to look for answers to frequently asked questions.
Building safety remediation programme for Wales
With 2024 October progress updates.
In major support package for small businesses.
Conservation and transformation
Reading Ruskin’s cultural heritage. Book review.
Renovating Union Chain Bridge.
AI tools for planning, design, construction and management
A long, continually expanding list, any more to add?