Milestones
Milestones are important project management tools that can be used as a component of project scheduling.
A milestone is a significant event that occurs during the course of a project, the timing of which can influence the scheduling of other activities. With the achievement of successive milestones, management is able to maintain a more accurate understanding of how the project is advancing according to the schedules.
Milestones might include, for example:
- Securing funding.
- Acquiring a site.
- Appointing consultants.
- Completing design stages.
- Client approvals.
- Securing permissions.
- Tendering the construction contract.
- Appointing a contractor.
- Handing over the site to the contractor.
- Starting and completing construction.
- Occupying the completed development.
- Rectifying defects.
Milestones are a feature of many project management software tools and often appear on Gantt charts, represented by diamond symbols. Developing schedule with milestones marked along a project programme can help give clarity to a timeline which can otherwise be very complex and difficult to interpret. This can be particularly useful for some stakeholders who may only need a very general understanding of a project programme.
They may coincide with key decisions or gateways at which the client assesses the state of development of the project and considers whether to progress to the next stage. However, it is important that milestones are allocated to the achievement of a task, not to the task itself.
For example, consultants often describe client decisions as milestones on project programmes, when in fact, the client may need to be provided with information to make a decision, they need time to consider that information, and they may then need to convene a meeting, which if they are senior personnel may only be possible on specific dates (such as at pre-planned board meetings).
Milestones are known as a ‘task of zero duration’ because they represent a particular point of time in a project when an achievement has been reached, they do not represent the activities necessary to complete a task.
They are often used to show progress on critical rather than non-critical activities, that is, items that represent a potential ‘bottleneck’ in the progress of a project. The overall critical path for a project represents the shortest time in which the project can be completed. Achieving milestones on the critical path more quickly than was planned will reduce the overall project programme.
However, this can serve to present a misleading impression of the overall health of the project, as project managers may prioritise resources into achieving critical milestones, whilst neglecting those works that are not identified as a milestone. This can change the critical path so that activities which were not previously critical become so.
To be useful tools in monitoring and controlling a project, project managers must be careful not to overuse milestones as a means of driving progress, whilst ensuring there is no loss in momentum as a result of spacing milestones too far apart. Instead, a compromise must be reached with milestones pinpointing suitably critical deliverables on a consistent basis, commonly at intervals of no longer than every fortnight for projects of several months duration.
Suitable remedies must be planned in the event that a milestone is missed. Resources may need to be reallocated to ensure they continue to be matched to priorities. However, it is important that milestones represent a challenge and should be treated as opportunities to make adjustments as the work is proceeding.
See also: Milestone payment.
[edit] Related articles
- Acceleration of construction works.
- Activity schedule.
- Benefits realisation milestone.
- Change control procedures.
- Contractor’s master programme.
- Critical path method.
- Data drops.
- Gantt chart.
- Gateways.
- How progress is agreed in construction.
- Key dates.
- Key performance indicators.
- Line of balance (LOB).
- Milestone payment.
- Pareto analysis.
- Programme consultant.
- Programme float.
- Programme for building design and construction.
- Progress of construction works.
- Project crashing.
- Project manager.
- Scheduling construction activities.
- Short period programme.
- Time-location chart.
- Time management of construction projects.
- Topping out.
- Transition point.
[edit] External references
Featured articles and news
50th Golden anniversary ECA Edmundson apprentice award
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Digital technology, transformation and cybersecurity
Supporting SMEs through Digitalisation in Construction.
Villa Wolf in Gubin, history and reconstruction. Book review.
Construction contract awards down one billion pounds
Decline over the past two months compared to the same period last year, follows the positive start to the year.
Editor's broadbrush view on forms of electrical heating in context.
The pace of heating change; BSRIA market intelligence
Electric Dreams, Boiler Realities.
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.