Acceleration of construction works
|
Acceleration is the process of speeding up the work of a contractor so that a particular activity, or the project as a whole, can be completed before the date required under the contract.
Generally, it is the client that requires the acceleration of construction work. A client might require that a building is handed over earlier than is set out in the contract or, where the contractor has been allowed an extension of time, may require completion earlier than the revised completion date. This is referred to as 'directed acceleration'.
Where the contractor incurs additional costs as a result of this sort of acceleration, it can result in a claim against the client. Typically, the contractor does not have to prove the works were actually completed more quickly than originally agreed, just that they made a reasonable attempt to do so and that the attempt resulted in additional costs.
Acceleration of the works may also be undertaken by the contractor voluntarily, if, for example, they wish to move on to another project, mitigate inefficiencies and delays that may have been incurred, or to save on costs. They may also be motivated by bonuses awarded for early completion. However, if acceleration is undertaken voluntarily, the contractor will not be able to claim additional costs from the client.
There are several techniques available for accelerating work:
- Working overtime.
- Adding new shifts.
- Providing additional labour.
- Additional supervision.
- Providing additional resources, such as plant and equipment.
- Re-sequencing work activities (also known as project crashing or fast tracking).
- Adopting alternative construction methods, such as off-site manufacturing.
- Changing the design or specification.
- Reducing the scope of the works (for example transferring responsibility for some works from the contractor to the client), and
- Early procurement of key items.
These techniques are likely to result in additional costs and may not guarantee early completion. While the same number of tasks need to be performed, they are condensed into a shorter period, and so are likely to require more resources. In addition, purchasing costs may be higher due to time pressures, incomplete information and the complexity of managing the interfaces between elements. A greater number of variations are also likely than on a traditional contract.
Options such as working overtime typically result in employees being paid at a higher rate (typically 1.5-2 times the regular rate).
Acceleration is also likely to result in additional risks. If resources are focused on critical-path activities, there is the possibility that non-critical-path activities will be affected. Quality, safety and compliance can be affected, and acceleration can result in an overall loss of productivity, perhaps due to tiredness on the part of workers being required to do overtime, or unfamiliarity of the site and the project on the part of additional workers being brought in.
It is recommended that acceleration agreements are prepared prior to the implementation of acceleration measures to clarify the position regarding factors such as cost, reward and risk.
For more information, see Agreement for the acceleration of construction works.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Agreement for the acceleration of construction works.
- Benchmark
- Critical path method.
- Expidite.
- Extension of time EOT.
- Fast track construction.
- How to prepare a claim for an extension of time.
- Milestones.
- Project benchmarking.
- Project crashing.
- Resource leveling.
- Resource management.
- Scheduling construction activities.
- Time-location chart.
- Time management of construction projects.
- Variations.
Featured articles and news
Reslating an ancient water mill
A rare opportunity to record, study and repair early vernacular roofs.
CIOB Apprentice of the Year 2025/26
Construction apprentice from Lincoln Mia Owen wins this years title.
Insulation solutions with less waste for a circular economy
Rob Firman, Technical and Specification Manager, Polyfoam XPS explains.
Recycled waste plastic in construction
Hierarchy, prevention to disposal, plastic types and approaches.
UK Net Zero Carbon Buildings Standard V1 published
Free-to-access technical standard to enable robust proof of a decarbonising built environment.
Prostate Cancer Awareness Month
Why talking about prostate cancer matters in construction.
The Architectural Technology podcast: Where it's AT
Catch up for free, subscribe and share with your network.
The Association of Consultant Architects recap
A reintroduction and recap of ACA President; Patrick Inglis' Autumn update.
The Home Energy Model and its wrappers
From SAP to HEM, EPC for MEES and FHS assessment wrappers.
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.




















