Agreement for the acceleration of construction works
Contents |
[edit] Introduction
Generally, it is the client that requires acceleration of construction work. A client might be anxious that its building is handed over earlier than is set out in the contract or, where the contractor has been allowed extensions of time, earlier than the revised completion date.
In the latter case an acceleration agreement can be used as a 'wrap up' agreement expunging all outstanding claims for extensions of time and loss and expense.
For more information, see Acceleration of construction works.
[edit] Contractor’s acceleration proposal
Before instructing the contractor to accelerate the works, there is a negotiating period, sometimes within a time frame stipulated in the construction contract. The contractor will put together a proposal that should include:
- Additional resources of manpower, plant and materials directly employed or subcontracted.
- The revised methodology and actions to be taken to achieve the accelerated date. This might include off-site prefabrication, extra scaffolding and temporary weatherproofing.
- A revised programme with target intermediate dates by which progress can be measured. This might include proposals for phased completion if this is advantageous to the client.
- A statement on working hours on- and off-site, including weekends, holidays, night working and shift working if applicable.
- Additional supervision and any other increased costs for items categorised as preliminaries.
- Any concessions made by the client to assist the programme which might include:
- Changes to design or specification (for example, standardisation replacing bespoke solutions).
- Reduction in scope (for example, transferring work to a separate post-contract agreement for occupational works).
- The terms of settlement of all outstanding claims. This will include payment that might be linked to achieving the revised programme milestone dates.
[edit] Client’s assessment of the acceleration proposal
The client’s consultant team should be asked to prepare a report on the contractor’s acceleration proposals, including a risk assessment of matters that may impede the contractor in achieving the revised programme.
The cost consultant in particular should comment on the validity of the detailed prices set out in the contractor’s proposal. The design team should comment on any proposed changes to the design or specification.
The client and consultant team might want to re-assess exactly how risk should be allocated in the work to be undertaken and whether any changes to the original contract might be appropriate. For instance, a reduction in the first month of liquidated and ascertained damages might lead to a reduction in the sum of money the contractor has put in their price for risk in case of failure to meet the revised completion date.
At the opposite extreme, a set of one-off bonus payments for each milestone achieved can encourage the contractor to go flat out, spending contingency money to collect the bonus payments.
In the end, only the client can weigh up whether or not the proposal represents value for money within the context of its business plan for the development .
[edit] The agreement
It is advisable to have an agreement drawn up by a lawyer reflecting the outcome of negotiations. It is usual for acceleration agreements to be treated as an addendum to the building contract. As such, it is advisable to have it drafted by the legal team that put together the original contract documents so that inconsistencies and ambiguities are avoided.
The agreement must also include details of:
- What happens if the contractor fails to implement some or all of the measures in its proposals?
- What happens if the contractor fails to meet intermediate targets and/or the completion date?
- The points at which each payment is due.
- Changes required to the existing contract documents to accommodate the acceleration agreement, including any changes to design or specification.
- The treatment of retention in respect of acceleration, claims and bonus payments.
[edit] Related articles on Designing Buildings
- Acceleration of construction works.
- Agreement.
- Construction contract.
- Constructive acceleration.
- Contractor's master programme.
- Critical path method.
- Design web.
- Earned value.
- Fast track construction.
- Information release schedules.
- Key performance indicators.
- Pareto analysis.
- Programme consultant.
- Progress in construction.
- Project crashing.
- Project programme.
- Scheduling construction activities.
- Time management of construction projects.
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.