Loss and expense
Construction contracts will generally provide for the contractor to claim direct loss and/or expense as a result of the progress of the works being materially affected by relevant matters for which the client is responsible, such as:
- Failure to give the contractor possession of the site.
- Failure to give the contractor access to and from the site.
- Delays in receiving instructions.
- Opening up works or testing works that then prove to have been carried out in accordance with the contract.
- Discrepancies in the contract documents.
- Disruption caused by works being carried out by the client.
- Failure by the client to supply goods or materials.
- Instructions relating to variations and expenditure of provisional sums.
- Inaccurate forecasting of works described by approximate quantities.
- Issues relating to CDM.
Claims may comprise costs resulting from disruption to the works or from delays to the works (prolongation).
The contractor must give written notice of a claim as soon as it becomes reasonably apparent that the regular progress of the works is being materially affected. This need not necessarily result in a delay to the completion date, and so claims for loss and expense and claims for extensions of time do not necessarily always run together.
Claims are restricted to 'direct' loss and expense and so 'consequential losses' (such as lost production) are generally excluded. Direct losses are those that 'flow naturally' from the breach of contract.
There is disparity between contract types about whether items such as head office overheads can be included in claims for loss and expense, and some court rulings have allowed such claims. If there are specific consequential losses which the parties to the contract wish to exclude, it may be prudent therefore to state these explicitly within the contract.
NB: The New Engineering Contract (NEC3) contains provision for the contractor to claim payment for 'compensation events' rather than loss and expense.
[edit] Related articles on Designing Buildings
- Business interruption cover under COVID-19.
- Causes of construction disputes.
- Civil procedure rules.
- Concurrent delay.
- Consequential loss.
- Contract claims.
- Contractual right.
- Cost overruns.
- Defects.
- Dispute resolution.
- Disruption claims in construction.
- Extension of time.
- Force majeure.
- Frustration.
- Head office overheads.
- Henry Boot Construction Ltd v Alstom Combined Cycles.
- Liquidated damages.
- Named specialist work.
- Payment for extra work.
- Professional indemnity insurance.
- Profit and overheads.
- Prolongation.
- Provisional sums.
- Relevant event.
- Right to payment.
- The distinction between liquidated damages clauses and penalty clauses.
- Variations.
- What is a default?
[edit] External references
- Ascertaining Loss and Expense RICS: ISBN 978 1 78321 114 2
Featured articles and news
STEM ambassadors needed for ICE CityZen award.
Digital gaming competition for UK students aged 16 to 18.
Heritage protection in England vs Australia.
Fire doors and the Fire Door Inspection Scheme.
Three-quarters of fire doors fail inspections
UN International Day for Biological Diversity, May 22.
The role of geoparks, biospheres and world heritage sites.
BSRIA conference 2022, June 23.
Just one month to go ! Find out more here.
Restoring Broadbent’s Bath House
A new gallery for the University of Huddersfield.
Corruption in the construction industry.
What will it take to stop it ?
To celebrate world bee day 2022 !
Just one month until the changes to part L come into effect.
Not forgetting part F and the new part overheating part O.
Heat Pump demand rises by one quarter.
As energy prices jump up in cost.
With people in the UK from Ukraine.
Industry leader Steve Murray takes on role.
An abundant and versatile building material.
How overheating complicates ending gas in the UK.
600,000 heat pump installations targeted per year by 2028.
Cost planning, control and related articles on DB.
Helping prevent those unwanted outcomes.
ICE debate Public transport - post pandemic.
How has transport changed due to Covid-19 ?
Cross-ventilation in buildings. Do you have it ?
Will you need it ? after June 15 and the new Part O ?
Share your knowledge with the industry.
Create an account and write the first of many articles.
The green jobs delivery group.
CIAT commentary after the first meeting.
Liverpool's world heritage site status
Who is to blame?
Research recommends focussing on portfolio success rather than project success.
Comments
According to JCT - Standard Building Contract , in Article 4.23 ...if Contractor incurs or likely to incur loss and expense for which he would not be reimbursed under any provision in these Conditions due to regular progress of Works or any part of them has been or is likely to be materially affected by any of the Relevant matters the Contractor may make an application to the Architect/Contract Administrator. If Architect is of the opinion that regular progress has been or likely to be materially affected ... issues a variation instruction.
in 4.24, a Relevant Matter is described to include the matter described above which is not initiated by Architect directly.
In 5.2, it is mentioned in text, Variations required by direct Architect's instructions as identical to ones (first encountered by Contractor as "differing site conditions" and brought to Architects attention) subsequently sanctioned by Architect in writing ( as a valid variation).
Thus, as opposed to many articles about JCT's being mute about "unforeseeable ground conditions") JCT includes "unforeseeable or differing site conditions clause " as a loss and expense item. Variation is normally considered as a modification of design, quality or quantity of Works instructed by Architect. For unforeseeable ground conditions, It is requested by Contractor first and then, ascertained and instructed by Architect as variation. If it is not instructed, it is a claim.
Therefore, please include "differing site conditions" as a loss and expense item in your list. It is like this in all English and American standard contracts except fidic silver book. This will make your list meaningful and complete.