Approximate quantities
A development of the elemental cost plan of estimating construction project costs, approximate quantities form part of an approximate quantities cost plan which represents a first attempt to measure defined quantities from drawings (or to ‘take them off’)
An approximate quantities cost plan is part of the iterative cost planning process and is a development of the elemental cost plan. Unlike the elemental cost plan (in which the cost of elements is broken down from the overall construction cost, based on the experience of the cost consultant and known costs of similar completed projects), the approximate quantities cost plan is a first attempt to measure defined quantities from drawings. In effect, it is a costed approximate bill of quantities.
The approximate quantities method is regarded as being more accurate and reliable than other estimating methods in showing where costs are distributed. In particular, it draws to the attention of designers those elements of the design that are standard and those that are not and which, as a consequence, may be more expensive.
Unlike the elemental method, the basis of the approximate method of estimating is the grouping together of diverse, combined items under a rate (known as a composite rate) which is calculated by combining the individual prices of the components in the group. Because the items grouped together have the same dimensions (whether in metres or square metres, or perimeter and area), it allows those items to be measured at the same time.
For example, under the approximate quantities method, items such as roofs can be grouped with soffits and ceilings; this would not occur in the elemental plan.
The approximate quantities cost plan can form a solid base for an effective value engineering exercise. However, it should be accompanied by a schedule of assumptions made and perhaps a cash flow projection. A pre-construction whole-life cost plan may also be prepared.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
STEM ambassadors needed for ICE CityZen award.
Digital gaming competition for UK students aged 16 to 18.
Heritage protection in England vs Australia.
Fire doors and the Fire Door Inspection Scheme.
Three-quarters of fire doors fail inspections
UN International Day for Biological Diversity, May 22.
The role of geoparks, biospheres and world heritage sites.
BSRIA conference 2022, June 23.
Just one month to go ! Find out more here.
Restoring Broadbent’s Bath House
A new gallery for the University of Huddersfield.
Corruption in the construction industry.
What will it take to stop it ?
To celebrate world bee day 2022 !
Just one month until the changes to part L come into effect.
Not forgetting part F and the new part overheating part O.
Heat Pump demand rises by one quarter.
As energy prices jump up in cost.
With people in the UK from Ukraine.
Industry leader Steve Murray takes on role.
An abundant and versatile building material.
How overheating complicates ending gas in the UK.
600,000 heat pump installations targeted per year by 2028.
Cost planning, control and related articles on DB.
Helping prevent those unwanted outcomes.
ICE debate Public transport - post pandemic.
How has transport changed due to Covid-19 ?
Cross-ventilation in buildings. Do you have it ?
Will you need it ? after June 15 and the new Part O ?
Share your knowledge with the industry.
Create an account and write the first of many articles.
The green jobs delivery group.
CIAT commentary after the first meeting.
Liverpool's world heritage site status
Who is to blame?
Research recommends focussing on portfolio success rather than project success.