Cost consultant
Typically cost consultants are quantity surveyors by profession, but accountants and other professionals can also be effective cost consultants.
The cost consultant provides estimates, and advice regarding the cost of construction works.
The cost consultant's role might include:
- Helping determine the client's requirements and undertaking feasibility studies.
- Benchmarking requirements against similar projects.
- Assessing and comparing options.
- Helping define the project budget.
- Checking developing designs against the project budget.
- Assessing value for money.
- Checking designs meet legal and quality standards.
- Undertaking risk management and value management exercises.
- Preparing cost plans, estimates and cash flow projections.
- Advising on procurement strategy.
- Advising on packaging.
- Preparing bills of quantities.
- Preparing tender pricing documents.
- Collating and issuing tender documentation.
- Assessing tenders.
- Estimating the cost of variations.
- Preparing valuation statements for interim certificates.
- Assisting with the valuation of claims.
- Preparing regular cost reports, including out-turn cost and cash flow.
- Completing the final account.
There are very many different names given to cost planning documents. Cost plans are generally prepared by cost consultants (often quantity surveyors). They evolve through the life of the project, developing in detail and accuracy as more information becomes available about the nature of the design, and then actual prices are provided by specialist contractors, contractors and suppliers. They range from very early initial cost appraisals through to tender pricing documents and the final account.
As a consequence there area a great number of names that can be used for key cost planning information. On Designing Buildings Wiki we have standardised these as follows:
- Initial cost appraisals (studies of options prepared during the feasibility study stage).
- Elemental cost plan (prepared during the project brief stage and carried through to detailed design).
- Approximate quantities cost plan (from the end of detailed design through to tender).
- Pre-tender estimate (prepared alongside tender documentation).
- Tender pricing document (strictly speaking this is not a priced document, but is part of the tender documentation issued to the contractor for pricing).
- Contract sum (agreed with the contractor during the tender period and adjusted during the construction period).
- Contract sum analysis (a break down of the contract sum prepared by the contractor on design and build projects).
- Final account (agreed during the defects liability period).
Other than initial cost appraisals, these all relate to the construction cost of the project (rather than wider project costs that the client might incur, which could include; fees, equipment costs, furniture, the cost of moving staff, contracts outside of the main works, and so on). It is important that the client makes clear what costs should be monitored by the cost consultant and what will remain within the control of the client organisation.
Initial cost appraisals are carried out without the benefit of a design for the project. They include client costs that may not feature in later cost plans and as a result will almost certainly need input from the client's finance director or financial advisers. Once the initial cost appraisal is completed, the client will decide the scope of costs that will in future be monitored by the cost consultant and those that will be monitored and controlled by the client organisation.
For detailed descriptions of the sequence of activities necessary to appoint a cost consultant, see the work plan stages:
- Traditional contract: appointment.
- Design and build: appointment.
- Public project: appointment.
- Construction management: appointment.
- Management contract: appointment.
[edit] Related articles on Designing Buildings
- Accounting.
- Approximate quantities cost plan.
- Bid writer.
- Budget.
- Building People.
- Business plan.
- Cash flow.
- Chartered surveyor.
- Commercial manager.
- Consulting engineer.
- Construction buyer.
- Contract sum analysis.
- Cost control.
- Cost savings.
- Cost and bonus surveyor.
- Cost plans.
- Elemental cost plan.
- Estimator.
- Final account.
- Front-loaded costs.
- Initial cost appraisal.
- Interim certificate.
- New Rules of Measurement.
- Pre-tender estimate
- Professional indemnity insurance.
- Whole life costing.
- Quantity surveyor.
- Sustainability quantity surveyor.
- Tender pricing document.
- Variations.
- Whole life solution
[edit] External references
Featured articles and news
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.
UKCW London to tackle sector’s most pressing issues
AI and skills development, ecology and the environment, policy and planning and more.
Managing building safety risks
Across an existing residential portfolio; a client's perspective.
ECA support for Gate Safe’s Safe School Gates Campaign.
Core construction skills explained
Preparing for a career in construction.
Retrofitting for resilience with the Leicester Resilience Hub
Community-serving facilities, enhanced as support and essential services for climate-related disruptions.
Some of the articles relating to water, here to browse. Any missing?
Recognisable Gothic characters, designed to dramatically spout water away from buildings.
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.





















