Budget for building design and construction projects
A budget is a statement of the amount of money that is available to spend over a period of time, or on a specific thing, such as a building. It may include an outline plan for how that money will be spent, and a breakdown of the items it will be spent on.
The CIOB Code of practice for project management 4th edition, defines a budget as:
'Quantification of resources needed to achieve a task by a set time, within which the task owners are required to work... a budget consists of a financial and/or quantitative statement, prepared and approved prior to a defined period, for the purpose of attaining a given objective for that period.'
Budgets for construction projects help determine what is affordable and should be set as early as possible. It is important that they are based on evidence and are realistic.
The RIBA Plan of Work 2013 defines the project budget as; 'The client’s budget for the project, which may include the construction cost as well as the cost of certain items required post -completion and during the project’s operational use.'
A project budget can be established by:
- Assessment of projected income and expenses through the life of the project.
- Comparison with similar projects.
- Assessment of the funds available.
- Pre-design analysis of requirements.
- Analysis of preliminary design options.
The project budget is set by the client and is distinct from cost plans prepared by a cost consultant which are likely to focus on the construction cost.
The client's total project budget may include:
- The construction cost.
- Land or property acquisition.
- Approvals fees.
- Planning costs (Section 106 Agreement or Community Infrastructure Levy).
- Financing costs.
- Site investigations.
- Fixtures, fittings and equipment.
- The cost of decanting and relocating, including costs associated with moving staff.
- Contracts outside of the main works.
- Insurance.
- Consultant fees.
- Inflation.
- Contingency.
- VAT.
It is common on projects that the project budget and the project brief diverge over time and it is for this reason that careful cost control is important.
It is important that the client makes clear what costs should be monitored by the cost consultant and what will remain within the control of the client organisation.
NB: NRM 1 defines the authorised budget (sometimes referred to as the approved estimate or cost limit) as; 'the maximum expenditure that the employer is prepared to make in relation to the completed building.'
NB: In the case of Riva Properties Ltd & Ors v Foster + Partners Ltd [2017], the Technology and Construction Court (TCC) found that Foster + Partners had been negligent in failing to design a hotel that could be constructed within Riva Properties budget, and then suggesting that it could be value engineered down to the budget after planning permission had been granted. Foster + Partners were held liable for client's costs of £3.6 million in developing the scheme which was almost £100 million over the budget.
Stephen Homer, a partner at Ashfords LLP, the lawyers that acted for Riva Properties said; "This case serves as a warning to designers that they cannot design in a vacuum. Cost and budget is a key constraint and should always be identified and considered when designing any project, even when the provision of cost advice is expressly excluded from the designer’s obligations."
[edit] Related articles on Designing Buildings
- Accounting.
- Approximate quantities cost plan.
- Benchmarking.
- Best value.
- Bills of quantities.
- Business case.
- Business plan.
- Capital.
- Capital allowances.
- Capital costs.
- Capital value.
- Commercial management.
- Contract sum.
- Contract sum analysis.
- Cost.
- Cost certainty.
- Cost consultant.
- Cost control.
- Elemental cost plan.
- Estimate.
- Final account.
- Green budgeting.
- Initial cost appraisals.
- Net Present Value.
- Pre-tender estimate.
- Price certainty.
- Whole-life costs.
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.
Comments
It would be apt to say that the ultimate success of a project manager and the construction company greatly depends on the fact whether their projects are completed on-time and on-budget. Essentially, construction project management is all about keeping track of the
costs at all stages of the project to ensure that you don’t flout the budget considerations.