Final account
Construction contracts generally provide some mechanism for the final payment to be made to the contractor on completion of the works described in the contract. Generally this payment will be made at the end of the defects liability period providing that all patent defects have been rectified.
Preparing the final account is the process of calculating and agreeing any adjustments to the contract sum (the amount originally set out in the contract to be paid to the contractor for completion of the works) so that the amount of the final payment can be determined. The amount of the final payment is then set out in the final certificate (or final statement). It is possible for the final certificate to show that money is owed to the client, rather than due to the contractor.
Construction contracts may not specifically require the preparation of a final account, although they generally do require the contractor to provide all documents necessary for the adjustment of the contract sum within a specified time, and set out the time scale for and consequences of issuing the final certificate.
The contract sum may need to be adjusted for a number of reasons, including:
- Variations.
- Fluctuations.
- Prime cost sums.
- Provisional sums.
- Payments to nominated sub-contractors or nominated suppliers.
- Statutory fees.
- Payments relating to the opening-up and testing of the works.
- Loss and expense.
- Liquidated and ascertained damages.
- Contra claims imposed as a result of the contractor's operations (such as a third-party claim resulting from contractor negligence or contractual breach, for example, flooding a neighbour's property).
- The release of any remaining retention.
Agreeing the final account can be a complicated, time consuming and adversarial process, often resulting in disputes. The process can be made easier if adjustments to the contract sum are agreed as the project progresses rather than saving them up for the end. It is also beneficial if the client's quantity surveyor and the contractor's quantity surveyor work together on drafts of the final account before agreement is sought. It is preferable that a draft copy of the final account is signed off by the contractor as an 'in full and final settlement' prior to issue.
Agreement of the final account will allow the contract administrator to issue the final certificate. The final certificate is conclusive that all patent defects have been remedied, all adjustments to the contract sum have been agreed and all claims settled. Latent defects may still become apparent after completion of the contract and these may give rise to action for damages, for breach of contract or negligence.
Where proceedings have begun in relation to a dispute, the conclusiveness of the final certificate is subject to the findings of those proceedings.
In addition, the final certificate itself can be disputed (usually within 28 days). Adjudication, arbitration or other dispute resolution procedures may then be necessary to resolve the dispute. The final certificate is then only conclusive in relation to matters that are not disputed.
If the client intends to pay a different amount from that shown on the certificate, they must give notice to the contractor of the amount they intend to pay and the basis for its calculation (a 'pay less notice' - see Housing Grants, Construction and Regeneration Act for more information).
See also: Outturn cost.
[edit] Related articles on Designing Buildings
- Accounting.
- Campaign for cash retentions reform.
- Contract sum.
- Contract sum analysis.
- Cost consultant.
- Cost plans.
- Cost reporting.
- Cost value reconciliation.
- Defects.
- Escrow.
- Final certificate.
- Fluctuations.
- Housing Grants, Construction and Regeneration Act.
- Liquidated damages.
- Loss and expense.
- New Rules of Measurement.
- Outturn cost.
- Pre-tender estimate.
- Prime cost sums.
- Provisional sums.
- Retention bond.
- Scott schedule.
- Tender pricing document
- Variations.
- Whole-life costs.
Featured articles and news
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.