Payments to nominated sub-contractors
A nominated sub-contractor is one that is selected by the client to carry out an element of the works and then imposed on the main contractor after the main contractor has been appointed. This allows the client to have direct, separate negotiations with major suppliers of goods or services and feed their appointment and design input into the contract after works by the main contractor have commenced.
There is no direct contractual relationship between the client and the nominated sub-contractor.
The main contractor is instructed by the client to use a nominated sub-contractor for a particular element of the works through the inclusion of a prime cost sum (based on the nominated sub-contractor’s accepted quotation) to which the main contractor is entitled to add mark up and attendance costs (such as material handling, use of site facilities, scaffolding, and so on).
The main contractor should specify the general preliminaries available to the nominated sub-contractor, and specific items of preliminaries to be provided by the sub-contractor.
Before any order is placed the main contractor should be consulted as to whether the sub-contractor's proposals are acceptable, including matters relating to preliminaries.
When the nominated sub-contractor works are being carried out, the client’s cost consultant will periodically value their work and the amount properly due is then shown as a separate amount on interim certificates. This amount is also notified to the nominated sub-contractor.
The contractor must then pay the nominated sub-contractor the certified amount. The contract may allow the client to pay the nominated sub-contractor directly if the main contractor fails to do so.
As the contractor has no choice in the selection of the nominated sub-contractor, they cannot be held responsible for failure of the nominated sub-contractor to perform. However, as the contract for the nominated sub-contractor is with the main contractor, not with the client, the client should ensure that they have a direct warranty with the nominated sub-contractor to guarantee performance and to indemnify the client if any default allows a claim for loss and expense or extension of time by the main contractor.
[edit] Related articles on Designing Buildings Wiki
- Construction supply chain payment charter.
- Domestic sub-contractor.
- Fair payment practices.
- Interim certificates.
- Main contractor’s discount.
- Named sub-contractor.
- Nominated sub-contractor.
- Nominated subcontractor v named subcontractor.
- Nominated supplier.
- Payment period.
- Prime cost sum.
- Procurement route.
- Remedies for late payment.
Featured articles and news
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.