Nominated sub-contractor
Contents |
[edit] Introduction
Sub-contractors are appointed by main contractors to carry out part of the works on their behalf. As construction has become more complicated and more specialist construction techniques have been developed, it has become increasingly common for contractors to sub-contract others rather than employing a large workforce themselves.
The use of sub-contractors enables the main contractor to undertake more complex projects whilst not unacceptably increasing their risk, however, concerns have been expressed about the prevalence of sub-contractors because of a perception that the main contractor has less control over the skills and training of sub-contractor employees and so there may be a negative impact on quality and health and safety on site.
Sub-contractors can be classified as:
- Domestic sub-contractors.
- Named sub-contractors.
- Nominated sub-contractors...
In addition, on management contracts, the works will be carried out by 'works contractors' and on construction management contracts the works will be carried out by 'trade contractors', although technically trade contractors are not sub-contractors as they are contracted by the client, and only managed by the construction manager.
[edit] Nominated sub-contractors
A nominated sub-contractor is one that is selected by the client to carry out an element of the works. Nominated sub-contractors are imposed on the main contractor after the main contractor has been appointed.
The mechanism for nominating is an instruction in relation to a prime cost sum to which the main contractor is entitled to add a mark-up and attendance costs. It allows the client to have direct separate negotiations with major suppliers of goods or services and feed their appointment and design input into the contract after works by the main contractor have commenced.
There are mutual benefits to the client and sub-contractor using the nomination route. The client can select the specialist contractor it wants, obtain design and value engineering input and have direct access during the progress of works. The sub-contractor benefits by having so much greater certainty of payment.
Examples of situations where sub-contractors might be nominated could include:
- Long delivery items where ordering is necessary before the appointment of the main contractor. For example, lifts, switchgear, or refrigeration plant.
- Where specialist design input is required in the early stages of design development. For example, for a cladding system.
- Where the client directly orders a preferred item on which design is to be based. For example complex or specialist industrial plant or equipment.
[edit] Contractual arrangements
The contractual arrangements allowing nomination are very complicated, attempting to cover all possible eventualities both between the client and the main contractor and also between the main contractor and the nominated sub-contractor. This may include; objections by the main contractor to the nomination, insolvency of the nominated sub-contractor, the need for re-nomination, and so on.
The contractor may or may not be held responsible for the failure of the nominated sub-contractor to perform, depending on the exact wording of the specific contract used. However, as the subcontractor is being imposed on them, the contractor will generally be allowed the right to object to the subcontractor under certain conditions. If the client still wishes to use the subcontractor, some contracts allow them to indemnify the main contractor against the possible consequences of this.
In addition, as the contract for the nominated sub-contractor is with the main contractor, not with the client, the client may wish to ensure that they have a direct warranty with the nominated sub-contractor to guarantee performance and to indemnify them against any possible losses.
Nomination is still common on international projects, but some forms of contract (such as Joint Contracts Tribunal (JCT) contracts) no longer include provision for nomination because of the complexities involved. The use of named sub-contractors or named specialists are generally considered to be a simpler alternative.
[edit] Payment
The cost consultant values the work of the nominated sub-contractor separately and the amount due is shown on interim certificates and is notified to the nominated sub-contractor. The contract may allow the client to pay the nominated sub-contractor directly if the main contractor fails to do so.
[edit] Allocation of preliminaries
The allocation of preliminaries between the main contractor and sub-contractor depends on whether the nominated sub-contractor is appointed before or after the main contractor.
Normally the main contractor is appointed first. In this case, it is wise to get the main contractor to specify the general preliminaries available to the sub-contractor, such as welfare buildings, craneage, site security, hoists, water, power and lighting, and general scaffolding, etc., but also to set out specific items of preliminaries to be provided by the sub-contractor, such as site offices and stores, special scaffolding or cranes and waste disposal to a certain point.
Before any order is placed the main contractor should be consulted as to whether the subcontractor's proposals are acceptable including matters relating to preliminaries.
If the sub-contractor is appointed before the main contractor, it is wise to send them the proposed preliminaries requirements to be imposed on the main contractor and request that the sub-contractor clearly states in their tender what preliminaries are included in their bid and what preliminaries they anticipate will be provided by the main contractor.
[edit] Public projects
NB: On public sector projects, a sub-contract for which the client intends to nominate a sub-contractor may be subject to the requirements of the OJEU procurement rules.
[edit] Related articles on Designing Buildings
- Collaborative practices.
- Construction supply chain payment charter.
- Contract sum.
- Contractor.
- Domestic sub-contractor.
- Named specialist work.
- Named sub-contractor.
- Nominated subcontractor v named subcontractor.
- Nominated supplier.
- OJEU.
- Payments to nominated sub-contractors.
- Preliminaries.
- Prime cost sum.
- Procurement route.
- Selected subcontractor.
- Subcontractor.
[edit] External references
- Building article: http://www.building.co.uk/what-sort-of-subbie-are-you?/3046823.article What sort of subbie are you?
- PACE http://webarchive.nationalarchives.gov.uk/20100503135839/http://www.ogc.gov.uk/documents/PACE_-_GACC.pdf Guidance for the Appointment of Consultants and Contractors.
Featured articles and news
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.