Named specialist work in construction
In February 2013, a change was introduced to the JCT Standard Building Contract 2011 enabling an employer to identify specialists to be used as domestic sub-contractors (that is specialists subcontracted by the main contractor) for identified parts of the works by appropriate entry in the contract particulars.
This provides the opportunity for the employer to select a sub-contractor with particular expertise, whilst leaving responsibility for their performance with the main contractor.
This is similar to provisions for named subcontractors in some other forms of contract, and its inclusion is seen to be a result of the omission of provisions for nominated subcontractors from the JCT Standard Building Contract since 2005.
If the naming of specialists is required, a series of standard clauses and amendments must be incorporated into the contract. There are two ways in which the specialist provisions can work:
- Pre-named specialist work: The specialist may be named in the contract together with the work to be carried out.
- Post-named specialist work: A provisional sum may be inserted in the bill of quantities, allowing the contract administrator to issue an instruction to name the specialist and identify the works required.
Upon receiving an instruction from the contract administrator in relation to a post-named specialist or a replacement specialist, the contractor is able to raise reasonable objection within seven days. The contract administrator then has a further seven days to either:
- Name an alternative specialist.
- Instruct the contractor to undertake the work itself or through its own sub-contractor.
- Omit the work altogether.
This may entitle to contractor to an extension of time and /or loss and expense.
The contractor should enter into a contract with the specialist as soon as ‘reasonably practicable’ using a JCT Standard Building Sub-Contract.
The contract administrator must be notified if a contract cannot be entered by the contractor as required. On receipt of this notification the contract administrator must provide instruction to the contractor to either:
- Remove or solve whatever is preventing the contract.
- Select an alternative specialist.
- Undertake the work itself.
- Omit the work altogether.
If the contractor wishes to terminate the specialist’s employment, they must notify the contract administrator and, if required, the employer. The contractor can only give notice of termination or of repudiation after 14 days, unless the specialist has become insolvent.
If the contractor terminates the specialist’s employment, the contract administrator must issue instructions to the contractor to either:
- Name an alternative specialist.
- Undertake the work itself or through its sub-contractor.
- Omit the work altogether.
If the named specialist becomes insolvent the contractor may be entitled to an extension of time and /or loss and expense.
[edit] Related articles on Designing Buildings Wiki:
- Articles of agreement.
- Attestation in construction.
- Construction contracts.
- Contract conditions.
- Contract documents.
- Extension of time.
- Intermediate Building Contract.
- Joint Contracts Tribunal.
- Loss and expense.
- Named subcontractor.
- Nominated subcontractor.
- Nominated subcontractor v named subcontractor.
- Operative.
- Reasonable objection to a named specialist.
- Repudiation.
- Selected subcontractor.
- Specialist subcontractor.
- Sub-contract.
- Subcontractor.
- Supplier.
[edit] External references
- ‘The JCT Standard Building Contract 2011’, CHAPPELL, D., John Wiley and Sons (2015)
Featured articles and news
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”