Articles of agreement
|
Contents |
[edit] Introduction
Contract documents for a construction contract will typically consist of:
- Contract drawings.
- Priced bill of quantities.
- Articles of agreement.
- Contract conditions.
- For contracts where there is a contractor’s designed portion: employer’s requirements, contractor’s proposals and contract sum analysis.
The ‘articles of agreement’ set out the core obligations of the parties involved. Typically, they consist of four sections:
- Recitals.
- Articles.
- Contract Particulars.
- Attestation.
By way of an example, the contents of the articles of agreement in the JCT Standard Building Contract (SBC) are set out below in more detail.
[edit] Recitals
Recitals contextualise the agreement, giving factual explanations for the basis of the contract. Seven recitals describe what is required and the events that have taken place.
[edit] First recital
Describes the work required by the employer, identifies the site, confirms the preparation of the design and bill of quantities.
[edit] Second recital
Confirms that a priced copy of the bill of quantities has been supplied by the contractor to the employer, with a priced activity schedule where required.
[edit] Third recital
Identifies the contract drawings.
[edit] Fourth recital
Identifies whether the employer is to be considered a contractor for tax deduction purposes under the Construction Industry Scheme.
[edit] Fifth recital
Refers to an information release schedule provided to the contractor by the employer (this is optional).
[edit] Sixth recital
Clarifies whether the works are to be carried out in sections.
[edit] Seventh recital
This only applies (along with three more recitals), where the contractor is obliged to complete design works under the provisions for a contractor’s designed portion.
[edit] Articles
These set out what is agreed between the parties.
[edit] Article 1
The obligation of the contractor, i.e. undertaking and completing the works subject to the contract documents.
[edit] Article 2
The obligation of the employer, i.e. to pay the contract sum or such other sum as becomes payable under the contract (through variations and/or correction of errors).
[edit] Article 3
Identifies the architect (or contract administrator) under the contract, and provides the employer with the power to maintain someone in the role of duty-holder (or employer’s agent).
[edit] Article 4
Identifies the quantity surveyor.
[edit] Article 5
Identifies the principal designer.
[edit] Article 6
Identifies the principal contractor.
[edit] Article 7
Makes reference to the right to adjudication in the event of any dispute.
[edit] Article 8
Makes reference to the right to arbitration in the event of any dispute.
[edit] Contract particulars
This section sets out the aspects of the contract that are particular to the project to which the contract relates. It is a schedule for the variables in the agreement and conditions. It is important that the variables are compatible with the relevant operating mechanism in the agreement, conditions and schedules as disputes may arise when either party applies the contract particulars information without proper reference to the operating clause.
Read more about contract particulars here.
[edit] Attestation
The attestation is the process of confirming that something is correct or genuine, or that a particular requirement has been met. It may be completed:
[edit] Under seal
Signed by both parties, witnessed and made clear that it is executed as a deed.
[edit] Under hand
A ‘simple contract’ that is signed just by the parties.
[edit] Related articles on Designing Buildings Wiki
- Agreement.
- Attestation in construction.
- Construction contracts.
- Contract conditions.
- Contract documents.
- Contract execution.
- Contract negotiation.
- Contracts under seal v under hand.
- Essentials of a contract.
- FIDIC.
- Intermediate Building Contract.
- Joint Contracts Tribunal.
- Named specialist work.
- NEC3.
- Period for reply.
- Procurement route.
- Sub-contract.
- Z clauses.
[edit] External references
- ‘The JCT 05 Standard Building Contract’ (2nd ed.), NDEKUGRI, I., RYCROFT, M., Butterworth-Heinemann (2009)
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings for people to come home to... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”

























