Period for reply
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. The third edition, NEC3 was published in 2005.
Many clauses within the NEC suite of contracts establish a period within which a task must be completed by referring to defined dates such as the ‘completion date’, the ‘defects date’, and so on. Some clauses establish a period within which one of the parties must respond to a communication from the other, such as the period for the submission of quotations for compensation events, acceptance of the programme and so on. However, where no such period has been prescribed, then the ‘period for reply’ applies.
The Engineering Construction Contract (ECC) states that:
‘If this contract requires the project manager, the supervisor, or the contractor to reply to a communication, unless otherwise stated in this contract, he or she replies within the period for reply.’
The period for reply is set out in the contract data part one, completed by the employer, and replies to communications must be made within that period, unless another period is stated in the contract. Where a specific time limit is defined within the contract for a particular reply then this will take precedence over the period for reply.
If the project manager fails to reply to a communication within the period for reply, this may constitute a compensation event. If the contractor fails to reply to a communication, then an adjustment may be made to the next payment reflecting the cost to the employer.
An exception to this is where the project manager and contractor agree to an extension before the reply is due.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Articles of agreement.
- Compensation event.
- Contract conditions.
- Defects.
- Delay damages.
- Disallowed cost.
- Extension of time.
- Key dates.
- NEC3.
- NEC contract change management systems.
- NEC early contractor involvement.
- Procurement route.
- Time Risk Allowance TRA.
- Variations.
- Z clauses.
[edit] External references
- ‘The New Engineering Contract: A Legal Commentary’, McINNIS, A., Thomas Telford (2001)
Featured articles and news
Can your business afford to ignore mental well-being?
£70 - 100 billion annually in UK construction sector.
Mental health in the construction industry
World Mental Health Day 10 October.
Construction awards provide relief in wake of ISG collapse
Spike in major infrastructure awards, housing up but short of targets, are ISG collapse impacts yet to come.
Biodiversity net gain with related updates and terms
Only 0.5% of applications subject to BNG in the context significant proposed changes to planning.
As political power has shifted from blue to red
Has planning now moved from brown to green?
The role of construction in tackling the biodiversity crisis
New CIOB Nature of Building digital series available now.
The Nature Towns and Cities initiative
Grants of up to 1 million for local councils and partners.
The continued ISG fall out October updates
Where to look for answers to frequently asked questions.
Building safety remediation programme for Wales
With 2024 October progress updates.
In major support package for small businesses.
Conservation and transformation
Reading Ruskin’s cultural heritage. Book review.
Renovating Union Chain Bridge.
AI tools for planning, design, construction and management
A long, continually expanding list, any more to add?
Robots in the construction industry
From cultural characterisations to construction sites.
Empowering construction with AI integration
New horizons with a human touch.
Key AI related terms to be aware of
With explanations from the UK government.
Comments