Period for reply
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. The third edition, NEC3 was published in 2005.
Many clauses within the NEC suite of contracts establish a period within which a task must be completed by referring to defined dates such as the ‘completion date’, the ‘defects date’, and so on. Some clauses establish a period within which one of the parties must respond to a communication from the other, such as the period for the submission of quotations for compensation events, acceptance of the programme and so on. However, where no such period has been prescribed, then the ‘period for reply’ applies.
The Engineering Construction Contract (ECC) states that:
‘If this contract requires the project manager, the supervisor, or the contractor to reply to a communication, unless otherwise stated in this contract, he or she replies within the period for reply.’
The period for reply is set out in the contract data part one, completed by the employer, and replies to communications must be made within that period, unless another period is stated in the contract. Where a specific time limit is defined within the contract for a particular reply then this will take precedence over the period for reply.
If the project manager fails to reply to a communication within the period for reply, this may constitute a compensation event. If the contractor fails to reply to a communication, then an adjustment may be made to the next payment reflecting the cost to the employer.
An exception to this is where the project manager and contractor agree to an extension before the reply is due.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Articles of agreement.
- Compensation event.
- Contract conditions.
- Defects.
- Delay damages.
- Disallowed cost.
- Extension of time.
- Key dates.
- NEC3.
- NEC contract change management systems.
- NEC early contractor involvement.
- Procurement route.
- Time Risk Allowance TRA.
- Variations.
- Z clauses.
[edit] External references
- ‘The New Engineering Contract: A Legal Commentary’, McINNIS, A., Thomas Telford (2001)
Featured articles and news
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.
Digital technology, transformation and cybersecurity
Supporting SMEs through Digitalisation in Construction.
Villa Wolf in Gubin, history and reconstruction. Book review.
Construction contract awards down one billion pounds
Decline over the past two months compared to the same period last year, follows the positive start to the year.
Editor's broadbrush view on forms of electrical heating in context.
Comments