NEC early contractor involvement
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. It was developed as a reaction to other more traditional forms of construction contract which have been portrayed by some as adversarial. NEC is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers (ICE).
On 27 November 2015, at the Alliancing Code of Practice Launch at ICE's headquarters in London, it was announced that NEC would publish ‘Early Contractor Involvement’ (ECI) clauses for NEC contracts to help improve project collaboration. Ref ICE.
This move came in response to the increasing trend for early collaboration, which can be essential for projects using processes such as Building Information Modelling (BIM). ICE suggest that early contractor involvement '...supports improved team working, innovation and planning to deliver value for money'.
Previously, NEC projects often contracted design development and construction planning separately from detailed design and construction. The new clauses mean that a single NEC3 Engineering and Construction Contract (ECC) can be used for both stages where contractors are taking part in the design development and construction planning stage.
Peter Higgins, leader of the drafting team for the clauses, said, "This will allow the contractor to be appointed under a two-stage Engineering and Construction Contract (ECC) before details of what is to be constructed have been fully developed and priced.
"Two approaches to ECI are covered by the new clauses. The employer can engage the contractor to assist their consultant in designing the project, as well as to design specific elements. Following agreement of prices for the construction stage, the employer then instructs the contractor to deliver the works, including any outstanding design, under standard ECC Option C (target contract with activity schedule) terms.
"Alternatively, the employer can appoint the contractor to carry out the design with assistance from their consultant. The employer then instructs the contractor to deliver the works under standard ECC Option C or E (cost reimbursable contract) terms. If using Option E, the contractor can also be incentivised to provide a cost-effective design by sharing in the savings on the employer's budget, which includes other relevant costs incurred by the employer."
The clauses are available as a free download now from http://www.neccontract.com. NEC will also be releasing an advisory 'How To' guide to the clauses in 2016.
[edit] Related articles on Designing Buildings Wiki
- Atkins v Secretary of State for Transport.
- Collaborative practices.
- Construction contract.
- Contract conditions.
- Contractor's design portion.
- Defined cost.
- Delay damages.
- Early appointment / involvement.
- Early contractor involvement.
- FIDIC.
- Institution of Civil Engineers.
- JCT.
- Latham Report
- Management contract.
- NEC contract change management systems.
- NEC contracts - road development and management schemes.
- NEC3.
- Optimised contractor involvement.
- Period for reply.
- Procurement route.
Featured articles and news
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties at 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.