NEC early contractor involvement
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration between the contractor and client. It was developed as a reaction to other more traditional forms of construction contract which have been portrayed by some as adversarial. NEC is a division of Thomas Telford Ltd, the commercial arm of the Institution of Civil Engineers (ICE).
On 27 November 2015, at the Alliancing Code of Practice Launch at ICE's headquarters in London, it was announced that NEC would publish ‘Early Contractor Involvement’ (ECI) clauses for NEC contracts to help improve project collaboration. Ref ICE.
This move came in response to the increasing trend for early collaboration, which can be essential for projects using processes such as Building Information Modelling (BIM). ICE suggest that early contractor involvement '...supports improved team working, innovation and planning to deliver value for money'.
Previously, NEC projects often contracted design development and construction planning separately from detailed design and construction. The new clauses mean that a single NEC3 Engineering and Construction Contract (ECC) can be used for both stages where contractors are taking part in the design development and construction planning stage.
Peter Higgins, leader of the drafting team for the clauses, said, "This will allow the contractor to be appointed under a two-stage Engineering and Construction Contract (ECC) before details of what is to be constructed have been fully developed and priced.
"Two approaches to ECI are covered by the new clauses. The employer can engage the contractor to assist their consultant in designing the project, as well as to design specific elements. Following agreement of prices for the construction stage, the employer then instructs the contractor to deliver the works, including any outstanding design, under standard ECC Option C (target contract with activity schedule) terms.
"Alternatively, the employer can appoint the contractor to carry out the design with assistance from their consultant. The employer then instructs the contractor to deliver the works under standard ECC Option C or E (cost reimbursable contract) terms. If using Option E, the contractor can also be incentivised to provide a cost-effective design by sharing in the savings on the employer's budget, which includes other relevant costs incurred by the employer."
The clauses are available as a free download now from http://www.neccontract.com. NEC will also be releasing an advisory 'How To' guide to the clauses in 2016.
[edit] Related articles on Designing Buildings Wiki
- Atkins v Secretary of State for Transport.
- Collaborative practices.
- Construction contract.
- Contract conditions.
- Contractor's design portion.
- Defined cost.
- Delay damages.
- Early appointment / involvement.
- Early contractor involvement.
- FIDIC.
- Institution of Civil Engineers.
- JCT.
- Latham Report
- Management contract.
- NEC contract change management systems.
- NEC contracts - road development and management schemes.
- NEC3.
- Optimised contractor involvement.
- Period for reply.
- Procurement route.
Featured articles and news
ECA Industry Awards 2024 shortlist revealed
22 leading businesses from across the electrotechnical and engineering services sector.
Government unveils Skills England strategy
Skills England to transform opportunities and drive growth.
New Government Hub for York Given Planning Green Light
For up to 2,600 civil servants, due for completion by 2028.
Construction Skills Certification Scheme cards
July update on Professionally Qualified and Academically Qualified Person Cards.
BSRIA Briefing 2024, November 22
Sustainable Futures: Redefining Retrofit for Net Zero Living.
The CLC on driving competency in the retrofit sector
Previously published roadmap on skills for net zero.
The first labour government King's speech in fifteen years
Construction industry reactions, support and some concern.
CIOB Retrofit of Buildings Technical Information Sheet
What retrofit is, the approach to be taken and processes to be followed.
Adapting Historic Buildings for Energy and Carbon Efficiency
Historic England advice note 18, free download published.
10 retrofit projects revisited 10 years after completion.
Information orders, building liability orders and SPVs
Key BSA terms and how they impact special purpose vehicles.
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.