Defined cost
A cost reimbursable contract (sometimes called a cost plus contract) is one in which the contractor is reimbursed the actual costs they incur in carrying out the works, plus an additional fee.
Their actual costs are calculated based on their accounts and records, rather than a pre-determined rate or price. However, not all costs can be accurately determined on a project-specific basis, some costs have only been incurred due to the contractor’s inefficiency, and not all costs are recoverable under the contract.
Options (C, D, E and F) of the NEC (New Engineering Contract), EEC contract (Engineering and Construction Contract), describe the costs that can be recovered by the contractor as the ‘defined cost’, whereas the costs that cannot be recovered are described as the ‘disallowed cost’.
Very broadly, the defined cost includes payments due to subcontractors and the cost of components for other works (such as plant, equipment, people and so on), minus the disallowed cost.
The contract stipulates that only amounts incurred to provide the works are recoverable as cost components. If an amount can be classified as one component, such as ‘equipment’, then it cannot also fall within another, such as ‘people’.
There are seven cost component criteria:
- People: Those directly employed or paid by the contractor to carry out the works.
- Equipment: Items provided by the contractor and used to provide the works.
- Plant and materials: Items intended to be used and included in the works.
- Charges: Cancellation charges arising from a compensation event, payment to public authorities, specialist services, and so on.
- Manufacture and design: Only apply if they are outside the working areas and wholly or partly designed specifically for the works.
- Design: Costs for the works and equipment only.
- Insurance: Does not actually facilitate cost recovery for the contractor. Costs that would otherwise be recoverable that have been paid by the insurer to the contractor are set off against the recoverable cost.
[edit] Related articles on Designing Buildings Wiki:
- Articles of agreement.
- Cost reimbursable contract.
- Delay damages.
- Disallowed cost.
- Latham Report.
- NEC3.
- NEC contract change management systems.
- NEC early contractor involvement.
- Right to payment.
- Variations.
- Works information.
- Z clauses.
[edit] External references
Featured articles and news
Fire doors and the Fire Door Inspection Scheme.
Three-quarters of fire doors fail inspections
UN International Day for Biological Diversity, May 22.
The role of geoparks, biospheres and world heritage sites.
BSRIA conference 2022, June 23.
Just one month to go ! Find out more here.
Restoring Broadbent’s Bath House
A new gallery for the University of Huddersfield.
Corruption in the construction industry.
What will it take to stop it ?
To celebrate world bee day 2022 !
Just one month until the changes to part L come into effect.
Not forgetting part F and the new part overheating part O.
Heat Pump demand rises by one quarter.
As energy prices jump up in cost.
With people in the UK from Ukraine.
Industry leader Steve Murray takes on role.
An abundant and versatile building material.
How overheating complicates ending gas in the UK.
600,000 heat pump installations targeted per year by 2028.
Cost planning, control and related articles on DB.
Helping prevent those unwanted outcomes.
ICE debate Public transport - post pandemic.
How has transport changed due to Covid-19 ?
Cross-ventilation in buildings. Do you have it ?
Will you need it ? after June 15 and the new Part O ?
Share your knowledge with the industry.
Create an account and write the first of many articles.
The green jobs delivery group.
CIAT commentary after the first meeting.
Liverpool's world heritage site status
Who is to blame?
Research recommends focussing on portfolio success rather than project success.
ICE and BSI launch revised PAS 128 standard.
The revised standard for mapping underground utilities.