Defined cost
A cost reimbursable contract (sometimes called a cost plus contract) is one in which the contractor is reimbursed the actual costs they incur in carrying out the works, plus an additional fee.
Their actual costs are calculated based on their accounts and records, rather than a pre-determined rate or price. However, not all costs can be accurately determined on a project-specific basis, some costs have only been incurred due to the contractor’s inefficiency, and not all costs are recoverable under the contract.
Options (C, D, E and F) of the NEC (New Engineering Contract), EEC contract (Engineering and Construction Contract), describe the costs that can be recovered by the contractor as the ‘defined cost’, whereas the costs that cannot be recovered are described as the ‘disallowed cost’.
Very broadly, the defined cost includes payments due to subcontractors and the cost of components for other works (such as plant, equipment, people and so on), minus the disallowed cost.
The contract stipulates that only amounts incurred to provide the works are recoverable as cost components. If an amount can be classified as one component, such as ‘equipment’, then it cannot also fall within another, such as ‘people’.
There are seven cost component criteria:
- People: Those directly employed or paid by the contractor to carry out the works.
- Equipment: Items provided by the contractor and used to provide the works.
- Plant and materials: Items intended to be used and included in the works.
- Charges: Cancellation charges arising from a compensation event, payment to public authorities, specialist services, and so on.
- Manufacture and design: Only apply if they are outside the working areas and wholly or partly designed specifically for the works.
- Design: Costs for the works and equipment only.
- Insurance: Does not actually facilitate cost recovery for the contractor. Costs that would otherwise be recoverable that have been paid by the insurer to the contractor are set off against the recoverable cost.
[edit] Related articles on Designing Buildings Wiki:
- Articles of agreement.
- Cost reimbursable contract.
- Delay damages.
- Disallowed cost.
- Latham Report.
- NEC3.
- NEC contract change management systems.
- NEC early contractor involvement.
- Right to payment.
- Variations.
- Works information.
- Z clauses.
[edit] External references
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Bridging the gap between clients and contractors
Concerns remain around contractor quality, capability, and delivery.
Construction Management, 10 June.
Heat pumps beat boilers in new home tests.
Building Safety Act implementation in Wales
CIAT to host industry panel on 26 June.
New and updated CLC building safety guidance.
New UK National Buildings Database.
Building Safety Wiki Interviews
Chief executive of the British Woodworking Federation.
Planning condition discharge in England and Wales
A brief explanation from a building compliance expert, with further links.
Overheating guidance and tools for building designers
Guidance for dealing with element of building fabric control that have increasing importance.
Shading for housing, a design guide
From the Good Homes Alliance and British Blind and Shutter Association.
UK Standard Skills Classification (SSC)
A shared framework for describing skills needs.
Social media ban consultation comes to close
CIOB urges UK Government to consider social media’s role in careers guidance in ban debate.
















