Works information
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration. The third edition, NEC3 was published in 2005.
The contract documentation under the NEC Engineering and Construction Contract (ECC) comprises:
- The form of agreement.
- Conditions of contract.
- Contract data (setting out information needed to operate the contract and identifying the documents which contain works information).
- Prices, activities schedules and bill of quantities.
- Works information (describing what is to be done on the site).
- Site information (describing the condition of the site before the work starts).
Works information specifies and describes the works the contractor is to provide and sets out any constraints to how the contractor provides the works. It is presented either in the documents which the contract data states it is in, or in an instruction given by the project manager in accordance with the contract (although this may constitute a compensation event).
Works information may be prepared both by the employer and the contractor. Employer’s works information sets out the works and constraints for the contractor. Contractor’s works information is prepared in relation to those parts of the works the contractor is required to design. The employer’s works information is identified in the contract data part one, whilst the contractor’s works information is identified in the contract data part two. Both sets of works information should be consistent, and where there is disagreement between them, priority is given to the employer’s works information.
It is important that the employer’s works information creates a complete and precise statement of the employer’s requirements so the risk the contractor may misinterpret or misunderstand them is minimised. Clear, unambiguous language should be used, subjective terms should be avoided and it should not include anything that repeats or contradicts the contract data or conditions of contract. References to standard specifications should be checked for consistency with other parts of the contract.
Works information might include:
- Technical information, specifications and drawings.
- Constraints for how the contractor provides the works, such as safety requirements.
- Work to be designed by the contractor.
Typically, the structure of works Information might include:
- A description of the works.
- General constraints on how the contractor provides the works.
- Contractor’s design.
- Completion.
- Programme.
- Quality assurance.
- Tests and inspections.
- Management of the works.
- Working with the employer and others.
- Services and other things to be provided.
- Health and safety.
- Subcontracting.
- Title.
- Acceptance or procurement procedure.
- Accounts and records.
- Parent company guarantees.
- Performance bonds.
- Advanced payment bonds.
- Low performance damages.
- Employer’s work specifications and drawings.
The contractor’s primary obligation is to provide the works in accordance with the employer’s works information. This means contractors are only obliged to do things the works information says they must do.
Defects are considered to be works not in accordance with the works information. Whether the works carried out by the contractor are considered defective therefore will be determined by what is described in the works information.
The contractor’s works information sets out their proposals and design details for any works which they are required to design. This cannot be prepared until the employer’s works Information has been prepared. Where the contractor puts forward alternative proposals that the employer accepts, the employer’s works information should be changed so that they are consistent.
NB The Concept and Developed Design Quality Best Practice Self-Assessment Tool, published by the Chartered Quality Institute (CQI) Construction Special Interest Group (ConSIG) in 2021 and updated in 2022, defines Works Information as a: ‘Pack of Data that forms part of the Construction contract. It defines in detail exactly what the construction team have to deliver - it can have both Client/Owner standard requirements and all specific project related data.’
[edit] Related articles on Designing Buildings
- Articles of agreement.
- Contract data.
- Contract documents.
- Contract documentation (documents that might be referred to in contracts).
- Defects.
- Defined cost.
- Delay damages.
- Disallowed cost.
- Latham Report.
- NEC3.
- NEC contract change management systems.
- NEC early contractor involvement.
- Variations.
- Z clauses.
Featured articles and news
Future Homes Standard Essentials launched
Future Homes Hub launches new campaign to help the homebuilding sector prepare for the implementation of new building standards.
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
























