Works information
NEC was first published in 1993 as the New Engineering Contract. It is a suite of construction contracts intended to promote partnering and collaboration. The third edition, NEC3 was published in 2005.
The contract documentation under the NEC Engineering and Construction Contract (ECC) comprises:
- The form of agreement.
- Conditions of contract.
- Contract data (setting out information needed to operate the contract and identifying the documents which contain works information).
- Prices, activities schedules and bill of quantities.
- Works information (describing what is to be done on the site).
- Site information (describing the condition of the site before the work starts).
Works information specifies and describes the works the contractor is to provide and sets out any constraints to how the contractor provides the works. It is presented either in the documents which the contract data states it is in, or in an instruction given by the project manager in accordance with the contract (although this may constitute a compensation event).
Works information may be prepared both by the employer and the contractor. Employer’s works information sets out the works and constraints for the contractor. Contractor’s works information is prepared in relation to those parts of the works the contractor is required to design. The employer’s works information is identified in the contract data part one, whilst the contractor’s works information is identified in the contract data part two. Both sets of works information should be consistent, and where there is disagreement between them, priority is given to the employer’s works information.
It is important that the employer’s works information creates a complete and precise statement of the employer’s requirements so the risk the contractor may misinterpret or misunderstand them is minimised. Clear, unambiguous language should be used, subjective terms should be avoided and it should not include anything that repeats or contradicts the contract data or conditions of contract. References to standard specifications should be checked for consistency with other parts of the contract.
Works information might include:
- Technical information, specifications and drawings.
- Constraints for how the contractor provides the works, such as safety requirements.
- Work to be designed by the contractor.
Typically, the structure of works Information might include:
- A description of the works.
- General constraints on how the contractor provides the works.
- Contractor’s design.
- Completion.
- Programme.
- Quality assurance.
- Tests and inspections.
- Management of the works.
- Working with the employer and others.
- Services and other things to be provided.
- Health and safety.
- Subcontracting.
- Title.
- Acceptance or procurement procedure.
- Accounts and records.
- Parent company guarantees.
- Performance bonds.
- Advanced payment bonds.
- Low performance damages.
- Employer’s work specifications and drawings.
The contractor’s primary obligation is to provide the works in accordance with the employer’s works information. This means contractors are only obliged to do things the works information says they must do.
Defects are considered to be works not in accordance with the works information. Whether the works carried out by the contractor are considered defective therefore will be determined by what is described in the works information.
The contractor’s works information sets out their proposals and design details for any works which they are required to design. This cannot be prepared until the employer’s works Information has been prepared. Where the contractor puts forward alternative proposals that the employer accepts, the employer’s works information should be changed so that they are consistent.
[edit] Find out more
Related articles on Designing Buildings Wiki:
- Articles of agreement.
- Contract data.
- Contract documents.
- Contract documentation (documents that might be referred to in contracts).
- Defects.
- Defined cost.
- Delay damages.
- Disallowed cost.
- Latham Report.
- NEC3.
- NEC contract change management systems.
- NEC early contractor involvement.
- Variations.
- Z clauses.
External references
Featured articles and news
Provisional findings show illegal cartels in the industry.
CIAT reporting from the Competition and Markets Authority.
Making sustainable construction number one priority.
The future of construction report.
Interview with ECA CEO.
The Building Safety Act 2022 today.
Many provisions came into force on June 28, 2022.
With room to expand.
An information packed session at the BSRIA conference.
Refurbishment, Energy Efficiency, Indoor air and process.
Considering building acoustics with the AT Journal.
Why building acoustic considerations must be non-negotiable.
Create a profile, write informed product articles and share.
Aluminium Composite Panels (ACP) is one example.
Top 50 Women in engineering 2022.
Inventors and innovators at ICE.
Life, death and art at the Stuart court. Book review.
Real estate, place adaptation and innovation.
Review and comment on the revised draft before July 11.
We are indeed now 10 years old, so go on and be bold !
Write about something you know, help us build and grow !
IHBC's 25th anniversary 2022 Aberdeen School.
A blended event and triumphant return.
New Construction Leadership Council Co-Chair selected.
Mark Reynolds succeeds Andy Mitchell as Co-Chair of CLC
Designing Buildings is 10 years old.
Types of work to existing buildings.
From alteration to deconstruction on DB.
Publication available
In the sunshine things get hotter.
Understanding temperature in buildings on DB.
Giving power to the consumer on the road to net-zero.
A call for home energy management to be modernised.
How many different types can you think of ?
50th anniversary of the first Pride parade UK.
Looking back and fourth to what still needs to be done.
Balkrishna Doshi wins Royal Gold Medal 2022.
Pioneering Indian environmental design Architect.
The greenest building is the one already built.
History of Temple Meads rewritten.
UK crying out for female tradespeople says CIOB research.
Currently standing at just 1%.
Find out more with BSRIA.
Changes come into force for F,L,O and S.