Contract documents for construction
See also Contractual documents for a list of documents that are commonly required by or referred to in a construction contract.
Contents |
[edit] Traditional contract
The contract documents set out the obligations and responsibilities of the parties to the contract. On a traditionally-procured, fully-designed construction project, the contract documents for suppliers such as the main contractor are likely to include:
- Article of agreement and conditions of contract, for completing as a simple contract (or as a deed).
- Working drawings.
- Bills of quantities.
- Specifications.
- Schedules of work.
- Perhaps an information release schedule. Consultants can be reluctant to produce information release schedules because of concerns about being held to the dates on the schedule (even where the progress of construction does not require information when the information release schedule proposes it). Failure to keep to the dates set out in the information release schedule may then be a matter for which the contractor can claim an extension of time and loss and/or expense.
- A schedule of tender adjustments or clarifications negotiated and agreed after the receipt of tenders and prior to the signing of the contract.
- The requirement for the contractor to provide a performance bond and to obtain collateral warranties from any sub-contractors or suppliers.
Both client and contractor should engross the contract by witnessed signatures prior to commencement of work. In practice the administrative effort of collating all necessary paperwork can be overtaken by the desire to begin construction. In such circumstances it becomes harder to sort out any disputes as to the content. There have been cases where the courts have had to interpret an implied contract when the contract has remained unsigned.
[edit] Design and build
On design and build projects, the contract documents may comprise:
- The articles of agreement and conditions of contract.
- The employer's requirements.
- The contractor's proposals.
- The contract sum analysis.
- Possibly bills of quantities (for some or all of the design).
[edit] Building information modelling
On projects that adopt building information modelling (BIM), the contract documents may also include:
- A model enabling amendment introducing a BIM protocol as part of the contract documents.
- A BIM protocol, which establishes specific obligations, liabilities and limitations on the use of building information models and can be used by clients to mandate particular working practices.
- Employer's information requirements, which define information that the employer wishes to procure to ensure that the design is developed in accordance with their needs and that they are able to operate the completed development effectively and efficiently. Suppliers respond to the employer's information requirements with a BIM execution plan.
Click here to see a diagram showing the relationship between contractual documents for BIM.
[edit] NEC3
The contract documentation under NEC contracts comprises:
- The form of agreement.
- Conditions of contract.
- Contract data.
- Prices, activities schedules, bill of quantities.
- Works information.
- Site information.
[edit] Pre-contract meeting
A pre-contract meeting is likely to take place after the contractor has been appointed. This is an opportunity to for the project team to meet (perhaps for the first time) and to plan their activities. The minutes of the pre-contract meeting may form part of contract documents (for all procurement routes) subject to the agreement of both parties.
[edit] Related articles on Designing Buildings
- Articles of agreement.
- Association of Consultant Architects TAC-1 launch and BIM
- Bills of quantities.
- Boilerplate.
- Conformed contract.
- Construction contract.
- Contract conditions.
- Contract engrossment.
- Contract execution.
- Contract negotiation.
- Contract notice.
- Contractual documents.
- Contractors proposals.
- Contract sum analysis.
- Employers requirements.
- Engrossment.
- Form of tender.
- Information release schedule.
- Manual of Contract Documents for Highway Works.
- Named specialist work.
- Performance bond.
- Pre-contract meeting.
- Prescriptive specification.
- Procurement route.
- Schedules of work.
- Smart contracts.
- Specifications.
- Supply contract.
- Tender.
- Tender documents.
- Working drawing.
Featured articles and news
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.























Comments