Information release schedule for construction
If not all the information required to construct the works has been prepared or issued when the tender documentation is issued, or the contract executed, then an information release schedule may be prepared which gives dates for the release of information from the consultant team. There may also be schedules for the release of information from contractors to the consultant team.
These schedules may also indicate procurement periods for major items and reasonable durations for design approval procedures. Without such information, schedules can be unrealistic or unachievable.
Schedules should be kept up to date and may be changed to reflect changes to the construction programme. Such changes should be brought to the attention of the client, and any implications for the project highlighted.
Schedules may include reasonable durations for design approval procedures, trigger dates for contractor or specialist design, dates for commencement of purchase or manufacture and dates for site delivery/installation. The inclusion of these dates is very beneficial in demonstrating that the information release dates are credible and realistic.
Schedules should also allow for the realistic resourcing of consultants staff by giving a sensible spread of workload. Consultants must ensure that they are entirely comfortable with the information release schedule prior to it being incorporated into any contract documents.
An information release schedule may form part of the tender documentation or contract documents. Consultants can be reluctant to produce information release schedules for this purpose because of concerns about being held to the dates on the schedule (even where the progress of construction does not require information when the information release schedule proposes it). Failure to keep to the dates set out in the information release schedule may then be a matter for which the contractor attempts to claim an extension of time an loss and/or expense.
If there is no information release schedule, the contractor's master programme may include dates for the release of information, which the consultant team may comment on, but should not approve. If there is no sort of schedule at all, it may be sensible for the contractor and the consultant team to agree one.
Even without an information release schedule, the contract is likely to require that information necessary for the contractor to complete the works is made available to them at a time that it is reasonably necessary for them to receive it.
Information release schedules may need to include specific release protocols where building information modelling (BIM) is used.
[edit] Related articles on Designing Buildings
- Building Information Modelling.
- Construction contract.
- Contractor's master programme.
- Design programme.
- Information request schedule.
- Pre-contract meeting.
- Programme.
- Programme consultant.
- Programme for building design and construction.
- Request for information.
- Schedule.
- Schedule of drawings.
- Short period programme.
- Tender works programme.
Featured articles and news
What they are, how they work and why they are popular in many countries.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.
How neural technologies could transform the design future
Enhancing legacy parametric engines, offering novel ways to explore solutions and generate geometry.
Key AI related terms to be aware of
With explanations from the UK government and other bodies.
From QS to further education teacher
Applying real world skills with the next generation.
A guide on how children can use LEGO to mirror real engineering processes.
Data infrastructure for next-generation materials science
Research Data Express to automate data processing and create AI-ready datasets for materials research.
Wired for the Future with ECA; powering skills and progress
ECA South Wales Business Day 2025, a day to remember.
AI for the conservation professional
A level of sophistication previously reserved for science fiction.
Biomass harvested in cycles of less than ten years.
An interview with the new CIAT President
Usman Yaqub BSc (Hons) PCIAT MFPWS.
Cost benefit model report of building safety regime in Wales
Proposed policy option costs for design and construction stage of the new building safety regime in Wales.
Do you receive our free biweekly newsletter?
If not you can sign up to receive it in your mailbox here.