Information release schedule for construction
If not all the information required to construct the works has been prepared or issued when the tender documentation is issued, or the contract executed, then an information release schedule may be prepared which gives dates for the release of information from the consultant team. There may also be schedules for the release of information from contractors to the consultant team.
These schedules may also indicate procurement periods for major items and reasonable durations for design approval procedures. Without such information, schedules can be unrealistic or unachievable.
Schedules should be kept up to date and may be changed to reflect changes to the construction programme. Such changes should be brought to the attention of the client, and any implications for the project highlighted.
Schedules may include reasonable durations for design approval procedures, trigger dates for contractor or specialist design, dates for commencement of purchase or manufacture and dates for site delivery/installation. The inclusion of these dates is very beneficial in demonstrating that the information release dates are credible and realistic.
Schedules should also allow for the realistic resourcing of consultants staff by giving a sensible spread of workload. Consultants must ensure that they are entirely comfortable with the information release schedule prior to it being incorporated into any contract documents.
An information release schedule may form part of the tender documentation or contract documents. Consultants can be reluctant to produce information release schedules for this purpose because of concerns about being held to the dates on the schedule (even where the progress of construction does not require information when the information release schedule proposes it). Failure to keep to the dates set out in the information release schedule may then be a matter for which the contractor attempts to claim an extension of time an loss and/or expense.
If there is no information release schedule, the contractor's master programme may include dates for the release of information, which the consultant team may comment on, but should not approve. If there is no sort of schedule at all, it may be sensible for the contractor and the consultant team to agree one.
Even without an information release schedule, the contract is likely to require that information necessary for the contractor to complete the works is made available to them at a time that it is reasonably necessary for them to receive it.
Information release schedules may need to include specific release protocols where building information modelling (BIM) is used.
[edit] Related articles on Designing Buildings
- Building Information Modelling.
- Construction contract.
- Contractor's master programme.
- Design programme.
- Information request schedule.
- Pre-contract meeting.
- Programme.
- Programme consultant.
- Programme for building design and construction.
- Request for information.
- Schedule.
- Schedule of drawings.
- Short period programme.
- Tender works programme.
Featured articles and news
Ebenezer Howard: inventor of the garden city. Book review.
The Grenfell Tower fire, eight years on
A time to pause and reflect as Dubai tower block fire reported just before anniversary.
Airtightness Topic Guide BSRIA TG 27/2025
Explaining the basics of airtightness, what it is, why it's important, when it's required and how it's carried out.
Construction contract awards hit lowest point of 2025
Plummeting for second consecutive month, intensifying concerns for housing and infrastructure goals.
Understanding Mental Health in the Built Environment 2025
Examining the state of mental health in construction, shedding light on levels of stress, anxiety and depression.
The benefits of engaging with insulation manufacturers
When considering ground floor constructions.
Lighting Industry endorses Blueprint for Electrification
The Lighting Industry Association fully supports the ECA Blueprint as a timely, urgent call to action.
BSRIA Sentinel Clerk of Works Training Case Study
Strengthening expertise to enhance service delivery with integrated cutting-edge industry knowledge.
Impact report from the Supply Chain Sustainability School
Free sustainability skills, training and support delivered to thousands of UK companies to help cut carbon.
The Building Safety Forum at the Installershow 2025
With speakers confirmed for 24 June as part of Building Safety Week.
The UK’s largest air pollution campaign.
Future Homes Standard, now includes solar, but what else?
Will the new standard, due to in the Autumn, go far enough in terms of performance ?
BSRIA Briefing: Cleaner Air, Better tomorrow
A look back at issues relating to inside and outside air quality, discussed during the BSRIA briefing in 2023.
Restoring Abbotsford's hothouse
Bringing the writer Walter Scott's garden to life.
Reflections on the spending review with CIAT.
Retired firefighter cycles world to raise Grenfell funds
Leaving on 14 June 2025 Stephen will raise money for youth and schools through the Grenfell Foundation.
Key points for construction at a glance with industry reactions.