Short period programme
Programmes describe the sequence in which tasks must be carried out so that a project, or part of a project, can be completed on time.
When deciding on the amount of detail that is required on a programme, it is important to consider what the programme is for. Senior management may require a more detailed breakdown, while operational management may require details of activities on a day-to-day basis. The level of planning tends to become more detailed as the project progresses, and once the contract stage is reached many contractors will prepare short period programmes.
Short-term or short period programmes allow the overall construction programme to be broken down into specific time periods that can then be scheduled in much greater detail.
On refurbishment or renovation projects of a relatively short duration, Short period programmes may be prepared on a daily basis for each trade employed on the project. On large projects, the short period programme may, in effect, act as a sub-programme that keeps the master programme up to date.
For example, a programme covering 3 weeks’ work might be produced, and at the end of the first week of this programme, another 3-week programme prepared for the following period that reflects progress, problems and any changes to be made.
Short period programmes offer the contractor a better means of controlling day-to-day operations on site and act as a useful method of communication between the site manager, the foreman, subcontractors and trades. They can also be used in toolbox talks in order to engage the workforce with the health and safety implications of the programme.
The short period programme may be prepared by a site-based planning engineer or construction manager. The main objectives of the short period programme are:
- To assist in the coordination of operations in the short term, especially when considering the continuity of work for trades and subcontractors.
- To keep the master contract programme under constant review.
- To highlight information requirements in the short term in order to meet planned completion dates for each stage of the work.
- To assess key material requirements.
- To keep senior site management informed of progress.
NB The Code of Estimating Practice, seventh edition, published by the Chartered Institute of Building (CIOB), suggests that the short term programme is:
The name given to the contractor’s strategic works programme for a particular section of the works. It should be a critical path network, integrated with the master programme and show, amongst other things, the resources to be used on each activity and their duration and the cost calculated by reference to the productivity that the resource is planned to achieve. |
[edit] Related articles on Designing Buildings Wiki
- Accepted programme.
- Activity schedule.
- Baseline programme.
- Contract documents.
- Contractor’s master programme.
- Critical path method.
- Design programme.
- Information release schedule.
- Key performance indicators.
- Lead time.
- Milestones.
- Pre-construction information.
- Programme.
- Programme consultant.
- Programme for building design and construction.
- Progress of construction works.
- Scheduling construction activities.
- Tender works programme.
[edit] External references
- ‘Construction Planning, Programming and Control’ (3rd ed.), COOKE, B., WILLIAMS, P., Wiley-Blackwell (2009)
Featured articles and news
CIOB Art of Building photo contest 2024
International showcase for the very best photography of the built environment.
Celebrating architecture's eloquent champions.
Unusual perspectives on 1960s’ thinking.
AI and the challenges to intellectual property
The legal landscape of adopting AI now and in the future.
Worrying landscape for Welsh construction SMEs revealed.
In recent risk factor analysis report completed by CIOB.
Construction Sport survey highlights risks of dehydration
Supporting construction workers to avoid dangers.
Can your business afford to ignore mental well-being?
£70 - 100 billion annually in UK construction sector.
Mental health in the construction industry
World Mental Health Day 10 October.
Construction awards provide relief in wake of ISG collapse
Spike in major infrastructure awards, housing up but short of targets, are ISG collapse impacts yet to come.
Biodiversity net gain with related updates and terms
Only 0.5% of applications subject to BNG in the context significant proposed changes to planning.
As political power has shifted from blue to red
Has planning now moved from brown to green?
The role of construction in tackling the biodiversity crisis
New CIOB Nature of Building digital series available now.
The Nature Towns and Cities initiative
Grants of up to 1 million for local councils and partners.
The continued ISG fall out October updates
Where to look for answers to frequently asked questions.
Building safety remediation programme for Wales
With 2024 October progress updates.
In major support package for small businesses.
Conservation and transformation
Reading Ruskin’s cultural heritage. Book review.