Short period programme
Programmes describe the sequence in which tasks must be carried out so that a project, or part of a project, can be completed on time.
When deciding on the amount of detail that is required on a programme, it is important to consider what the programme is for. Senior management may require a more detailed breakdown, while operational management may require details of activities on a day-to-day basis. The level of planning tends to become more detailed as the project progresses, and once the contract stage is reached many contractors will prepare short period programmes.
Short-term or short period programmes allow the overall construction programme to be broken down into specific time periods that can then be scheduled in much greater detail.
On refurbishment or renovation projects of a relatively short duration, Short period programmes may be prepared on a daily basis for each trade employed on the project. On large projects, the short period programme may, in effect, act as a sub-programme that keeps the master programme up to date.
For example, a programme covering 3 weeks’ work might be produced, and at the end of the first week of this programme, another 3-week programme prepared for the following period that reflects progress, problems and any changes to be made.
Short period programmes offer the contractor a better means of controlling day-to-day operations on site and act as a useful method of communication between the site manager, the foreman, subcontractors and trades. They can also be used in toolbox talks in order to engage the workforce with the health and safety implications of the programme.
The short period programme may be prepared by a site-based planning engineer or construction manager. The main objectives of the short period programme are:
- To assist in the coordination of operations in the short term, especially when considering the continuity of work for trades and subcontractors.
- To keep the master contract programme under constant review.
- To highlight information requirements in the short term in order to meet planned completion dates for each stage of the work.
- To assess key material requirements.
- To keep senior site management informed of progress.
NB The Code of Estimating Practice, seventh edition, published by the Chartered Institute of Building (CIOB), suggests that the short term programme is:
| The name given to the contractor’s strategic works programme for a particular section of the works. It should be a critical path network, integrated with the master programme and show, amongst other things, the resources to be used on each activity and their duration and the cost calculated by reference to the productivity that the resource is planned to achieve. |
[edit] Related articles on Designing Buildings Wiki
- Accepted programme.
- Activity schedule.
- Baseline programme.
- Contract documents.
- Contractor’s master programme.
- Critical path method.
- Design programme.
- Information release schedule.
- Key performance indicators.
- Lead time.
- Milestones.
- Pre-construction information.
- Programme.
- Programme consultant.
- Programme for building design and construction.
- Progress of construction works.
- Scheduling construction activities.
- Tender works programme.
[edit] External references
- ‘Construction Planning, Programming and Control’ (3rd ed.), COOKE, B., WILLIAMS, P., Wiley-Blackwell (2009)
Featured articles and news
Building Safety recap February, 2026
Our regular run-down of key building safety related events of the month.
Planning reform: draft NPPF and industry responses.
Last chance to comment on proposed changes to the NPPF.
A Regency palace of colour and sensation. Book review.
Delayed, derailed and devalued
How the UK’s planning crisis is undermining British manufacturing.
How much does it cost to build a house?
A brief run down of key considerations from a London based practice.
The need for a National construction careers campaign
Highlighted by CIOB to cut unemployment, reduce skills gap and deliver on housing and infrastructure ambitions.
AI-Driven automation; reducing time, enhancing compliance
Sustainability; not just compliance but rethinking design, material selection, and the supply chains to support them.
Climate Resilience and Adaptation In the Built Environment
New CIOB Technical Information Sheet by Colin Booth, Professor of Smart and Sustainable Infrastructure.
Turning Enquiries into Profitable Construction Projects
Founder of Develop Coaching and author of Building Your Future; Greg Wilkes shares his insights.
IHBC Signpost: Poetry from concrete
Scotland’s fascinating historic concrete and brutalist architecture with the Engine Shed.
Demonstrating that apprenticeships work for business, people and Scotland’s economy.
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.