Short period programme
Programmes describe the sequence in which tasks must be carried out so that a project, or part of a project, can be completed on time.
When deciding on the amount of detail that is required on a programme, it is important to consider what the programme is for. Senior management may require a more detailed breakdown, while operational management may require details of activities on a day-to-day basis. The level of planning tends to become more detailed as the project progresses, and once the contract stage is reached many contractors will prepare short period programmes.
Short-term or short period programmes allow the overall construction programme to be broken down into specific time periods that can then be scheduled in much greater detail.
On refurbishment or renovation projects of a relatively short duration, Short period programmes may be prepared on a daily basis for each trade employed on the project. On large projects, the short period programme may, in effect, act as a sub-programme that keeps the master programme up to date.
For example, a programme covering 3 weeks’ work might be produced, and at the end of the first week of this programme, another 3-week programme prepared for the following period that reflects progress, problems and any changes to be made.
Short period programmes offer the contractor a better means of controlling day-to-day operations on site and act as a useful method of communication between the site manager, the foreman, subcontractors and trades. They can also be used in toolbox talks in order to engage the workforce with the health and safety implications of the programme.
The short period programme may be prepared by a site-based planning engineer or construction manager. The main objectives of the short period programme are:
- To assist in the coordination of operations in the short term, especially when considering the continuity of work for trades and subcontractors.
- To keep the master contract programme under constant review.
- To highlight information requirements in the short term in order to meet planned completion dates for each stage of the work.
- To assess key material requirements.
- To keep senior site management informed of progress.
NB The Code of Estimating Practice, seventh edition, published by the Chartered Institute of Building (CIOB), suggests that the short term programme is:
The name given to the contractor’s strategic works programme for a particular section of the works. It should be a critical path network, integrated with the master programme and show, amongst other things, the resources to be used on each activity and their duration and the cost calculated by reference to the productivity that the resource is planned to achieve. |
[edit] Related articles on Designing Buildings Wiki
- Accepted programme.
- Activity schedule.
- Baseline programme.
- Contract documents.
- Contractor’s master programme.
- Critical path method.
- Design programme.
- Information release schedule.
- Key performance indicators.
- Lead time.
- Milestones.
- Pre-construction information.
- Programme.
- Programme consultant.
- Programme for building design and construction.
- Progress of construction works.
- Scheduling construction activities.
- Tender works programme.
[edit] External references
- ‘Construction Planning, Programming and Control’ (3rd ed.), COOKE, B., WILLIAMS, P., Wiley-Blackwell (2009)
Featured articles and news
A change to adoptive architecture.
A must read for all built environment professionals.
A sun, tide, mass or scratch dial.
A brief description of time in the sun.
ICE Trustee Board update June 2022
Given by ICE President Ed McCann.
Artificial intelligence and project management
Two new research reports published by APM.
Association for Project Management membership offer
50% off APM Associate membership for Designing Buildings users.
Building safety, a shifting landscape for professionals
A commentary from the insurance perspective.
In brief with further links.
Walter Segal: self-built architect
A definitive book on a pioneer of green architecture.
Funding for heritage on the high street
Using heritage as a catalyst for reviving historic centres.
Commonwealth Heads of Government Meeting update.
Declaration prioritising sustainable urbanisation adopted.
A small hidden, often distant but key building component.
Some brief words about the actuator.
CIAT Chief Executive steps down.
After 34 years at the Institute.
Volunteer opportunity launched by the ICE
To support the next generation of engineers.
Provisional findings show illegal cartels in the industry.
CIAT reporting from the Competition and Markets Authority.
Making sustainable construction number one priority.
The future of construction report.
Interview with ECA CEO.
Many provisions came into force on June 28, 2022.
With room to expand.
An information packed session at the BSRIA conference.
Refurbishment, Energy Efficiency, Indoor air and process.
Create a profile, write informed product articles and share.
Aluminium Composite Panels (ACP) is one example.
We are indeed now 10 years old, so go on and be bold !
Write about something you know, help us build and grow !