Baseline programme
A baseline programme may be prepared by a contractor at the beginning of a project. This is a detailed view of how they will divide the works into activities, the duration of those activities, and logic links to preceding and succeeding activities. This programme should be practicable and realistic, showing when the contractor intends to carry out each part of the works and identifying the resources they intend to use.
Under NEC3 contracts, the contractor’s programme is then submitted to the project manager, and if the project manager accepts it, it becomes the ‘accepted programme’ identified in the contract data.
The contractor’s programme is likely to be updated throughout the course of the works and when accepted by the project manager, that updated programme becomes the new accepted programme.
NEC4 introduces the new concept of ‘treated acceptance’, by which the project manager has a specified period of time to notify the contractor whether their programme has been accepted or not. If they fail to notify the contractor within this period, the programme is deemed to be accepted.
NB The CIOB Planning Protocol 2021 (CIOB PP21), a technical information sheet published by the Chartered Institute of Building (CIOB) in February 2021, defines a baseline programme as: ‘A programme typically prepared prior to the commencement of a project, representing a contractor’s planned intention for sequencing the works. This programme is later used as a baseline for measuring the contractor’s actual progress and performance.’
[edit] Related articles on Designing Buildings Wiki
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.
The adaptive reuse of large industrial structures.
Promoting the circular economy by extending the life of buildings.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.
Construction Management, 17 June
Government rolls out digital planning tool to all local authorities.
Your views needed - a strategy for the professions, trades and occupations.
Confronting competency, codes, capacity and costs.

















