Logic link
Logic links describe the relationships between one activity and another.
Common types of logic link include:
- Finish-to-start: One activity cannot start until a previous activity has finished.
- Lagged finish-to-start: One activity cannot start until a specific amount of time after a previous activity has finished.
- Start-to-start: One activity cannot start until another activity has started.
- Lagged start-to-start: One activity cannot start until a specific amount of time after another activity has started.
- Finish-to-finish: One activity cannot finish until another activity has finished.
- Lagged finish-to-finish: One activity cannot finish until a specific amount of time after another activity has finished.
- Lagged start and finish: One activity cannot start until a specific amount of time after another activity has started, and it cannot finish until a specific amount of time after that activity has finished.
- Negative lag: One activity can start a specific amount of time before another activity has been completed.
- Must start / must finish. The activity must start or finish on a specific date.
Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
ECA Industry Awards 2024 shortlist revealed
22 leading businesses from across the electrotechnical and engineering services sector.
Government unveils Skills England strategy
Skills England to transform opportunities and drive growth.
New Government Hub for York Given Planning Green Light
For up to 2,600 civil servants, due for completion by 2028.
Construction Skills Certification Scheme cards
July update on Professionally Qualified and Academically Qualified Person Cards.
BSRIA Briefing 2024, November 22
Sustainable Futures: Redefining Retrofit for Net Zero Living.
The CLC on driving competency in the retrofit sector
Previously published roadmap on skills for net zero.
The first labour government King's speech in fifteen years
Construction industry reactions, support and some concern.
CIOB Retrofit of Buildings Technical Information Sheet
What retrofit is, the approach to be taken and processes to be followed.
Adapting Historic Buildings for Energy and Carbon Efficiency
Historic England advice note 18, free download published.
10 retrofit projects revisited 10 years after completion.
Information orders, building liability orders and SPVs
Key BSA terms and how they impact special purpose vehicles.
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.