Start-start logic
The CIOB Planning Protocol 2021 (CIOB PP21), a technical information sheet published by the Chartered Institute of Building (CIOB) in February 2021, defines start-start logic as: ‘Logic between activities / milestones which specifies the sequence that the predecessor activity is to start at the same time that the successor activity is to start.’
See also: Start-finish logic and Finish-start logic.
--CIOB
[edit] Related articles on Designing Buildings Wiki
- Accepted programme.
- Activity schedule.
- As-built programme.
- CIOB articles.
- Contractor's master programme.
- Contractor's working schedule.
- Critical path.
- Design programme.
- Finish-start logic.
- Logic link.
- Programme for building design and construction (project programme).
- Programme.
- Schedule.
- Start-finish logic.
- Stress test.
Featured articles and news
Ending decades of frustration, misinformation and distrust.
Essential tools in managing historically significant landscapes.
Classroom electrician courses a 'waste of money'
Say experts from the Electrical Contractors’ Association.
Wellbeing in Buildings TG 10/2025
BSRIA topic guide updates.
With brief background and WELL v2™.
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.