Accepted programme
Within the NEC Engineering and Construction Contract (ECC), the ‘accepted programme’, is identified within the Contract Data.
The contractor prepares a programme for the works, which is then submitted to the project manager for their approval. If it is approved, this becomes the 'accepted programme'. The programme should be practicable and realistic, showing when the contractor intends to carry out each part of the works and identifying the resource they intend to use. Ref. NEC Dictionary.
The contract may also require that a revised programme is prepared regularly, setting out the sequence of activities, progress, and the effect of compensation events. This must then be submitted to the project manager, and if accepted, this becomes the accepted programme, sometimes referred to as the updated programme. The final updated programme will show the as-built programme.
Within the ECC, the ‘activity schedule’ allocates a price to each activity undertaken during the works. This simplifies the administration of the interim payment process. The accepted programme shows how the activities on the activity schedule are programmed. The accepted programme and the activity schedule need not show exactly the same activities, but there should be correlation between them, and they should be kept up to date.
Without an accepted programme the contract cannot be administered properly. Under such circumstances, 25% of payments can be withheld, and it is not possible to assess compensation events.
Accepting the programme does not discharge the contractor of any responsibility, it simply accepts that the programme is realistic and that it can be used to assess future changes. If the programme is not accepted by the project manager, reasons for not accepting it must be given.
Reasons might include:
- It is not practical.
- It does not show required information.
- It does not properly represent the actual programme for activities.
- It does not show the full works.
Failure to accept or reject a programme may constitute a compensation event.
NEC4 introduces the new concept of ‘treated acceptance’, by which the project manager has a specified period of time to notify the contractor whether the programme has been accepted or not. If they fail to notify the contractor within this period, the programme is deemed to be accepted.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Baseline programme.
- Compensation event.
- Contract conditions.
- Contract data.
- Contractor's master programme.
- Defined cost.
- Delay damages.
- Disallowed cost.
- Early warning notice.
- Key dates.
- NEC contract change management systems.
- NEC early contractor involvement.
- NEC3.
- Programme.
- Programme for building design and construction.
- Programme narrative.
- Progress in construction.
- Short period programme.
- Tender works programme.
- Time Risk Allowance TRA.
- Works information.
- Z clauses.
Featured articles and news
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.






















