Programme narrative
A programme is a tool that can be used to divide works into a series of activities, each with a duration and logic links to preceding and succeeding activities. The programme may be depicted as a Gantt chart, line of balance diagram, pure logic diagram, time-scaled logic diagram or time-chainage diagram.
Within the NEC Engineering and Construction Contract (ECC), the ‘accepted programme’, is accepted by the project manager and should be a practicable and realistic representation of when the contractor intends to carry out each part of the works, identifying the resource they intend to use.
The programme narrative is a written explanation of the assumptions underlying the accepted programme (or the updated programme), its key resources, sequencing restraints, critical path, risks, exclusions, exceptions, and execution strategy.
Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
NB The CIOB Planning Protocol 2021 (CIOB PP21), a technical information sheet published by the Chartered Institute of Building (CIOB) in February 2021, defines programme narrative as: ‘an accompanying written narrative to a submitted programme which describes the characteristics of a programme and areas of non-conformance with stress tests.’
[edit] Related articles on Designing Buildings Wiki
- Accepted programme.
- Activity schedule.
- Contractor's master programme.
- Early warning notice.
- Key dates.
- NEC contract change management systems.
- NEC early contractor involvement.
- NEC3.
- Programme for building design and construction.
- Programme.
- Progress in construction.
- Short period programme.
- Stress test.
- Tender works programme.
- Time Risk Allowance TRA.
- Works information.
Featured articles and news
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description fron the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.
Futurebuild and UK Construction Week London Unite
Creating the UK’s Built Environment Super Event and over 25 other key partnerships.
Welsh and Scottish 2026 elections
Manifestos for the built environment for upcoming same May day elections.
Advancing BIM education with a competency framework
“We don’t need people who can just draw in 3D. We need people who can think in data.”
Guidance notes to prepare for April ERA changes
From the Electrical Contractors' Association Employee Relations team.
Significant changes to be seen from the new ERA in 2026 and 2027, starting on 6 April 2026.
First aid in the modern workplace with St John Ambulance.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.

























