Programme narrative
A programme is a tool that can be used to divide works into a series of activities, each with a duration and logic links to preceding and succeeding activities. The programme may be depicted as a Gantt chart, line of balance diagram, pure logic diagram, time-scaled logic diagram or time-chainage diagram.
Within the NEC Engineering and Construction Contract (ECC), the ‘accepted programme’, is accepted by the project manager and should be a practicable and realistic representation of when the contractor intends to carry out each part of the works, identifying the resource they intend to use.
The programme narrative is a written explanation of the assumptions underlying the accepted programme (or the updated programme), its key resources, sequencing restraints, critical path, risks, exclusions, exceptions, and execution strategy.
Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
NB The CIOB Planning Protocol 2021 (CIOB PP21), a technical information sheet published by the Chartered Institute of Building (CIOB) in February 2021, defines programme narrative as: ‘an accompanying written narrative to a submitted programme which describes the characteristics of a programme and areas of non-conformance with stress tests.’
[edit] Related articles on Designing Buildings Wiki
- Accepted programme.
- Activity schedule.
- Contractor's master programme.
- Early warning notice.
- Key dates.
- NEC contract change management systems.
- NEC early contractor involvement.
- NEC3.
- Programme for building design and construction.
- Programme.
- Progress in construction.
- Short period programme.
- Stress test.
- Tender works programme.
- Time Risk Allowance TRA.
- Works information.
Featured articles and news
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties at 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.
Could AI and VR cause an increase the value of heritage?
The Orange book: 2026 Amendment 4 to BS 7671:2018
ECA welcomes IET and BSI content sign off.



















