Programme narrative
A programme is a tool that can be used to divide works into a series of activities, each with a duration and logic links to preceding and succeeding activities. The programme may be depicted as a Gantt chart, line of balance diagram, pure logic diagram, time-scaled logic diagram or time-chainage diagram.
Within the NEC Engineering and Construction Contract (ECC), the ‘accepted programme’, is accepted by the project manager and should be a practicable and realistic representation of when the contractor intends to carry out each part of the works, identifying the resource they intend to use.
The programme narrative is a written explanation of the assumptions underlying the accepted programme (or the updated programme), its key resources, sequencing restraints, critical path, risks, exclusions, exceptions, and execution strategy.
Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
NB The CIOB Planning Protocol 2021 (CIOB PP21), a technical information sheet published by the Chartered Institute of Building (CIOB) in February 2021, defines programme narrative as: ‘an accompanying written narrative to a submitted programme which describes the characteristics of a programme and areas of non-conformance with stress tests.’
[edit] Related articles on Designing Buildings Wiki
- Accepted programme.
- Activity schedule.
- Contractor's master programme.
- Early warning notice.
- Key dates.
- NEC contract change management systems.
- NEC early contractor involvement.
- NEC3.
- Programme for building design and construction.
- Programme.
- Progress in construction.
- Short period programme.
- Stress test.
- Tender works programme.
- Time Risk Allowance TRA.
- Works information.
Featured articles and news
Scottish parents prioritise construction and apprenticeships
CIOB data released for Scottish Apprenticeship Week shows construction as top potential career path.
From a Green to a White Paper and the proposal of a General Safety Requirement for construction products.
Creativity, conservation and craft at Barley Studio. Book review.
The challenge as PFI agreements come to an end
How construction deals with inherited assets built under long-term contracts.
Skills plan for engineering and building services
Comprehensive industry report highlights persistent skills challenges across the sector.
Choosing the right design team for a D&B Contract
An architect explains the nature and needs of working within this common procurement route.
Statement from the Interim Chief Construction Advisor
Thouria Istephan; Architect and inquiry panel member outlines ongoing work, priorities and next steps.
The 2025 draft NPPF in brief with indicative responses
Local verses National and suitable verses sustainable: Consultation open for just over one week.
Increased vigilance on VAT Domestic Reverse Charge
HMRC bearing down with increasing force on construction consultant says.
Call for greater recognition of professional standards
Chartered bodies representing more than 1.5 million individuals have written to the UK Government.
Cutting carbon, cost and risk in estate management
Lessons from Cardiff Met’s “Halve the Half” initiative.
Inspiring the next generation to fulfil an electrified future
Technical Manager at ECA on the importance of engagement between industry and education.
Repairing historic stone and slate roofs
The need for a code of practice and technical advice note.
Environmental compliance; a checklist for 2026
Legislative changes, policy shifts, phased rollouts, and compliance updates to be aware of.




















