Duration
An activity is an operation or process consuming time and possibly other resources. An individual or work team can manage an activity. It is a measurable element of a programme.
The term ‘duration’ refers to the length of time needed to complete an activity. The time period can be determined inductively, by determining the start and finish date of an activity or deductively by calculation from the time necessary to expend the resources applied to the activity.
Ref Society of Construction Law Delay and Disruption Protocol, 2nd edition, February 2017, published by the Society of Construction Law (UK). https://www.scl.org.uk/resources/delay-disruption-protocol
[edit] Related articles on Designing Buildings Wiki
- Building completion.
- Certificate of non completion.
- Completion.
- Completion date.
- Concurrent delay.
- Contract completion date.
- Contractor’s planned completion date
- Extension of time.
- Loss and expense.
- Practical completion.
- Progress of construction works.
- Scheduling construction activities.
- Sectional completion.
- Time at large.
- Programme.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
More of England’s ‘hidden heroes’ will be celebrated.
CIAT calls for retrofit to be a priority.
Version 6 is now available, along with guidance for ECA members.
Post-War Homes: mid-century British architecture. Book review.
CIAT reflects on the party conferences.
CIOB announce the winners of the Art of Building photography competition.
National Scheme of Delegation introduced.
The cost of employing people remains a concern.
Code of Practice for Electrical Energy Storage Systems.
ECA calls on members to comment on draft 4th edition.
Bringing together expertise and creating cultural benefits.
CIOB celebrates positive Ofsted report.
The Building Safety Regulator announces a call for evidence.