Contractor’s planned completion date
The contractor’s planned completion date is the date shown on the contractor’s programme as being the date when the contractor plans to complete the works under the contract.
Ref Society of Construction Law Delay and Disruption Protocol, 2nd edition, February 2017, published by the Society of Construction Law (UK). https://www.scl.org.uk/resources/delay-disruption-protocol
[edit] Related articles on Designing Buildings Wiki
- Building completion.
- Certificate of non completion.
- Completion.
- Completion date.
- Concurrent delay.
- Defects liability period.
- Extension of time.
- Liquidated and ascertained damages.
- Loss and expense.
- Practical completion.
- Progress of construction works.
- Sectional completion.
- Time at large.
- Topping out.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Building Safety Regulator, 19 August
Gill Kernick appointed Independent Chair of Residents’ Panel.
Connecting knowledge, technology and conservation
Building competence for the future of built heritage.
Building Regulations and Building Safety Act
CIOB publishes free advice for non-domestic clients.
Building Safety Newsletter from MHCLG.
An extraordinary record of steel engineering worldwide.
Households living near new pylons to save on bills.
ECA warns growth must not outpace grid capacity or skills.
The role of the client and decision making
CIOB response to built environment professions call for evidence.
Construction's sustainability reporting revolution
Tracking upfront embodied carbon with digital tools.
ECA welcomes procurement reforms
Public spending must back British jobs and skills.
Campaigning for Edinburgh: the Cockburn Association 1875-2049
The role of the civic voice in protecting character. Book review.
CIOB photography competition is open for entries.