Delay analysis
Contents |
[edit] Introduction
Construction projects are often subject to delays, irrespective of whether the contractor is or is not to blame. A delay claim for one day (or however number of days are involved) means the construction scheduled for that day was not completed, which could have severe financial implications and adversely affect the project's progress.
Delay analysis identifies why delays occur on a construction project and the impact they are expected to have on the overall programme. The outcome of the analysis may lead to legal action brought by one party to the contract.
[edit] Who is responsible
Delays in construction can be the contractor’s fault:
Not the contractor’s fault:
- Unusual weather conditions.
- Interruption in material supply, particularly if material is imported.
- Strikes.
- Conflicting or missing information in contract documents.
- Failure to give the contractor possession of the site.
Irrespective of who is at fault, such delays may have a critical financial impact on the project. When they occur, they represent a deviation from the planned programme of work and the contractor may be able to seek a time extension to compensate for the delay. In this case, they can submit a claim to the client outlining the cause and reasons for the delay. The client (or an agent acting on behalf of the client) must then evaluate whether the claim is justified and whether the contractor is entitled to compensation. Analysing who is at fault for the delay is a highly complex process and one which may lead to disputes.
Delay analysis can be undertaken
- Prospectively: Predicting what effect the delay will have on the project’s progress, prospective analysis can be used before and after the effect of the delay has occurred.
- Retrospectively: Retrospective techniques evaluate the effect that the delay will have on the project but they can only be applied once the works have been completed.
- Contemporaneously: During the delay.
The Delay and Disruption Protocol of The Society of Construction Law sets out six methods of delay analysis:
- Impacted As-Planned Analysis.
- Time Impact Analysis.
- Time Slice Windows Analysis.
- As-Planned versus As-Built Windows Analysis.
- Retrospective Longest Path Analysis.
- Collapsed As-Built Analysis.
For more information see: https://www.scl.org.uk/sites/default/files/SCL_Delay_Protocol_2nd_Edition_Final.pdf
[edit] Related articles on Designing Buildings Wiki
- Breach of contract
- Collateral warranty.
- Construction contract.
- Contract v tort.
- Contracts under seal v under hand.
- Disputes.
- Letter of intent.
- Privity of contract.
- Retrospective longest path analysis.
- Rights of third parties.
[edit] External references
Featured articles and news
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.