Retrospective longest path analysis
Network analysis can help identify the interrelationships between tasks that make up complex processes and establish the most appropriate timing and sequence for their execution. The critical path is the path through the network that requires the longest period of time to progress from start to completion. This is the minimum timeframe necessary to complete the whole project.
Retrospective longest path analysis involves the determination of the retrospective as-built critical path.
This first requires the development of a detailed as-built programme. It is then possible to trace the longest continuous path backwards from the actual completion date to determine the as-built critical path. The incidence and extent of critical delay can then be determined by comparing key dates along the as-built critical path with the corresponding planned dates in the baseline programme. It is then possible to study project records to determine which events may have caused any critical delays identified.
This method only has limited capacity to recognise changes to the critical path during the course of the works.
Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Heritage staff wellbeing at work survey.
A five minute introduction.
50th Golden anniversary ECA Edmundson apprentice award
Showcasing the very best electrotechnical and engineering services for half a century.
Welsh government consults on HRBs and reg changes
Seeking feedback on a new regulatory regime and a broad range of issues.