Possession of the site by the contractor
Contracts generally grant the contractor exclusive possession of the site until practical completion when a handover meeting takes place and possession reverts to the client (see Handover to client).
The contract may state the date for possession of the site by the contractor (or commencement date), or, if not, then the site must be handed over to the contractor within a reasonable time after signing of the contract.
If the client fails to give possession of the site to the contractor, and there are no provisions for delay in the contract, then they will be in breach of contract. Even if the contract does provide for delay in giving possession of the site to the contractor, the contractor will still be able to claim for an extension of time and perhaps loss and expense.
A formal handover meeting when the contractor takes possession of the site is an opportunity to:
- Handover keys.
- Discuss issues related to continued occupation of any part of the site (particularly on refurbishment projects) such as access.
- Discuss security.
- Issue any significant information about the site (such as site services, tree preservation orders, etc.).
- Discuss ongoing maintenance, operation and protection issues regarding existing structures, landscape or other features to be retained.
- Discuss noise and dust reduction measures.
- Verify insurance provisions.
- Read meters.
- Provide contact details for key personnel on both sides.
- Discuss access for client's personnel and representatives or other client contractors.
See also Pre-contract meeting. The pre-contract meeting is an important meeting that takes place after the contractor has been appointed but before work commences on site. It is an opportunity to for the project team to meet (perhaps for the first time) and to plan the construction stage.
On certification of practical completion, the contractor will give possession of the site back to the client (see Handover to client).
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.